Transport · Road / tunnel
A9 Dualling — Pitlochry to Killiecrankie
Transport Scotland is preparing to upgrade 6.4 kilometres of the A9 trunk road between Pitlochry and Killiecrankie from single to dual carriageway. The scheme is a component of the wider programme to dual the A9 between Perth and Inverness and aims to improve journeys, road safety and resilience along a major Scottish north-south transport corridor. It will provide new dual-carriageway road sections, grade-separated junctions and improvements for walking and cycling, with associated bridge and drainage construction.[1]
Current position
Advance investigations and demolition have taken place; an October traffic notice scheduled railway drainage works. Transport Scotland announced its intention to award the £220.02 million main contract in October, with main dualling still to begin.
Project facts
Location: Perth and Kinross, Scotland
Length: 6.4 kilometres
Investment: £220.02 million intended main construction contract
Status: Enabling works under way; main dualling still to begin
Delivery authority: Transport Scotland
Target opening: By the end of 2030
Engineering work
The route requires substantial bridge and structural work. Transport Scotland's earlier scheme documentation identifies nine new or replacement bridges, including a major River Tummel crossing alongside the existing Tummel Bridge, works around Loch Faskally and Clunie Bridge, and a crossing of the Highland Main Line railway.[2][3]
Flood-mitigation and drainage works are integrated into the proposal, while junction changes seek to reduce conflict points between local traffic and the A9. The scheme also includes routes and access for pedestrians and cyclists, including connections with paths used around Killiecrankie.
Funding and procurement
On 20 October 2026 the Scottish Government announced its intention to award the main construction contract to Wills Bros Civil Engineering Ltd at an indicated £220.02 million. The award remained subject to the mandatory standstill period and completion of procurement, so the announcement does not prove that Wills Bros has begun the main roadworks.
The wider A9 Perth–Inverness dualling programme is described by the Scottish Government as a £3.97 billion investment.
Advance works
Site preparation recorded by October 2026 included archaeological investigation and demolition of vacant buildings. An October traffic notice scheduled Network Rail drainage-crossing works beneath the Highland Main Line, and Geo Rope’s advance tree clearance was scheduled from November 2026 to March 2027.
The main dual-carriageway construction was still to begin when Transport Scotland announced its intention to award the principal contract in October 2026.
Why it matters
The project would complete a substantial new dual-carriageway link on Scotland's main north-south road corridor, including complex bridge crossings and railway-interface engineering. It is a long-term transport-capacity and safety investment rather than a short-lived operational intervention.
Timeline
Prior to 2026
Statutory consents for the A9 Pitlochry–Killiecrankie scheme obtained.
2025
Tender shortlist includes Wills Bros, Kier and Balfour Beatty.
October 2026
Earlier enabling investigations and demolition reported; an October notice schedules railway drainage-crossing work.
20 October 2026
Government announces intention to award £220.02m main works contract to Wills Bros, subject to standstill.
22 October 2026
Transport Scotland details 2026/27 preparation programme.
From November 2026 (planned)
Extensive advance vegetation clearance, subject to actual delivery.
By end 2030 (target)
New dual carriageway scheduled to open to traffic.