Agratas completes utilities building steel framework
Cladding installation has begun on the utilities building at the Somerset factory, alongside work on the main manufacturing building.
Agratas is building a battery-cell factory at the Gravity campus near Bridgwater, Somerset. The plant is intended to supply electric-vehicle batteries, initially for Jaguar Land Rover.[1][2]
Agratas reported in September 2026 that Building One was nearly watertight and approaching internal fit-out. The council’s September programme forecast 2,500–2,900 construction workers from that autumn, with revised workforce accommodation, travel and construction transport plans required to be agreed and active before the increase.
Cladding installation has begun on the utilities building at the Somerset factory, alongside work on the main manufacturing building.
Agratas says construction employment at its electric-vehicle battery plant in Somerset will rise to about 2,900 workers as the project moves through its next delivery phase.