Airbus began building a 6,221m² extension to its Belfast wing-manufacturing facility in August 2026 to expand the production of composite wings for the A220 passenger aircraft. The development adds factory floorspace, specialist tooling and a third autoclave for curing carbon-fibre components.[1][2][3]

Technology And Capacity

Belfast is the exclusive production site for A220 wings, using a composite manufacturing process that reduces wing-structure weight relative to conventional aluminium designs. The extension is intended to support Airbus's programme-wide expansion towards 13 A220 aircraft per month by 2028. This rate is a future aircraft-production objective, not measured current output from the Belfast plant.

Additional Works

The manufacturer's broader Belfast programme also includes upgraded substations, factory access, office accommodation, a larger car park and IT infrastructure. Airbus has not disclosed a separate capital cost for the 6,221m² factory extension.

Delivery

Construction commenced by 19 August 2026. Airbus expects the extension to be complete during the first half of 2028, after installation of manufacturing equipment and supporting facilities.

Map information

The pin represents the existing Airbus wing-manufacturing facility; the precise footprint of the extension is not shown. [4]

Timeline

19 August 2026
Airbus confirms construction is underway.

2026
Factory and site infrastructure modernisation in progress.

First half 2028
Expected completion of wing facility extension.

2028
Airbus A220 production programme targets up to 13 aircraft monthly.