Aldi Bardon Automated Distribution Centre
Aldi has invested more than £500 million in a large automated distribution centre at Bardon, Leicestershire, which began operations in May 2026. The 1.3 million-square-foot site adds national grocery storage and replenishment capacity, with automated handling systems for ambient, chilled and frozen goods.[1][2][3][4][5][6]
Capacity
The complex consists of five linked buildings, incorporating high-bay automated storage, temperature-controlled chambers and 140 HGV loading bays. Aldi expects the centre to be able to handle nearly seven million pallets annually and serve almost 350 UK stores once fully operational in 2027. These are planned peak capabilities rather than activity already achieved.
Automation And Energy
Technology installed with Dematic and Cimcorp automates movement and retrieval of pallets and individual cases, including temperature-sensitive fruit and vegetables. Aldi installed approximately 19,000 solar panels on the roof. The centre is expected to employ around 1,000 people, including staff transferring from existing Aldi warehouses.
Delivery
The first goods left Bardon in May 2026. Fresh-produce operations started in September, including automated chilled handling. The facility is open and in use, with progressive ramp-up towards the operator's 2027 capacity targets.
Map information
The pin uses the distribution centre postcode as a representative location within the wider campus.
Timeline
August 2020
Planning approval.
April 2021
Groundworks begin.
2024
Main warehouse building completed.
28 May 2026
Aldi announces first goods leaving the new centre.
16–17 September 2026
Fresh-produce deliveries and dispatch begin.
2027
Target for full operational capacity.