Transport · Airport
Birmingham Airport upgrades
Birmingham Airport is delivering a phased programme of arrivals, baggage-handling and airfield improvements through 2029. Works include aircraft stands, taxiways, runway repairs and terminal heating and cooling systems.[1]
Current position
The airport reported expanded South immigration and baggage-reclaim facilities in July 2026, increasing its capacity to process arriving passengers.
Project details
- The £300 million capital programme was announced in October 2025. A separate £230 million debt package supports the airport’s investment.
- The airport’s wider £2 billion draft master plan is a separate proposal.
Timeline
May 2025
£230 million debt financing completed.
October 2025
£300 million four-year capital plan announced.
July 2026
Airport reports expanded South immigration and baggage reclaim.[2]
2029
End of the announced investment period.