Birnbeck Pier’s replacement deck reaches quarter mark
Four of 16 replacement deck spans are in place at the Grade II* listed pier. North Somerset Council marked the milestone on 28 September and continues to target public reopening in summer 2027.
Heritage & Culture · Heritage site
North Somerset Council is restoring the Grade II* listed Birnbeck Pier and associated buildings in Weston-super-Mare after decades of closure.[1][2]
Four of the pier’s 16 replacement deck spans are in place. The council expects public reopening in summer 2027; later island-building and north-jetty phases have separate timetables.
Four of 16 replacement deck spans are in place at the Grade II* listed pier. North Somerset Council marked the milestone on 28 September and continues to target public reopening in summer 2027.