Corscale appoints delivery team for Court Lane campus
Construction Enquirer reported McLaren and Phoenix ME’s pre-construction appointment on 3 June 2026, with enabling works planned from 1 July.
Corscale’s planned Court Lane campus at Iver would replace a 14-acre industrial estate beside the M25 with two data-centre buildings and an on-site substation.[1]
McLaren Construction and Phoenix ME were appointed under a pre-construction services agreement. Their announcement scheduled site clearance and enabling works from 1 July 2026 and targeted practical completion in the fourth quarter of 2029.
Construction Enquirer reported McLaren and Phoenix ME’s pre-construction appointment on 3 June 2026, with enabling works planned from 1 July.