Cranswick is carrying out a £100 million redevelopment of its pork-processing factory at Preston, near Hull, to expand meat-processing capacity and integrate automated storage and handling on site. A new automated cold-store system is already operational, with further processing-plant expansion in progress.[1][2][3][4][5]

The Investment

The multi-phase programme includes automated freezing, case sorting and pallet handling, additional chilled and frozen storage, and new factory processing infrastructure. Bringing these functions together on the same site reduces transfers between separate facilities and the amount of manual handling needed in production.

Production Capacity

Cranswick plans to increase processing capacity from approximately 35,000 to 50,000 pigs per week, an increase of roughly 40%. The company's 2026 annual report identifies improved operational efficiency and lower storage and energy costs as expected benefits. The higher throughput is the planned outcome of the full scheme.

Delivery

The automated on-site cold store was operational by May 2026. Construction and equipment upgrades continue on the wider £100 million programme, which the company expects to complete following its financial year ending in March 2027.

Map information

The pin uses the photographed entrance of the existing Preston factory as a representative site location; the exact location of each new building is not identified. [6]

Timeline

2025
Phased factory and abattoir modernisation in progress.

19 May 2026
Cranswick confirms automated on-site cold storage operating.

August 2026
Annual report reiterates expansion and expected 50,000-pig weekly capacity.

After March 2027
Company target for completion of the remaining programme.