DLR Fleet Replacement
TfL is introducing 54 new DLR trains with supporting depot works. Fleet introduction is phased; three trains were in passenger service at the October 2026 report.[1]
Current position
Delivery delayed: Full-fleet availability has moved from the earlier end-2026 expectation to end-2028.
Following modifications and testing, passenger service resumed on 7 September 2026. The October report records three trains operating; depot works continue.
Delivered and outstanding
- The new trains provide walk-through carriages, air conditioning, live information and dedicated wheelchair spaces.
- Most of the ordered fleet is not yet in passenger service. TfL targets all 54 by end-2028, subject to performance monitoring.
Timeline
30 September 2025
First new train entered passenger service.
4 November 2025
New trains temporarily withdrawn following a wet-weather braking issue.[3]
7 September 2026
Passenger service resumed after modifications and assurance.