Current position
Development consent was granted on 27 October 2026. Construction has not been confirmed.
Project facts
Location: North-west of Newark-on-Trent, Nottinghamshire
Developer: Elements Green
Category: Energy — Solar Power and Battery Storage
Status: Approved — development consent granted 27 October 2026
Solar output: Up to 800 MW AC
Battery storage: 440 MW / 880 MWh used as an illustrative assessment scenario[2]
Expected construction: 2027 indicative, unconfirmed
Solar generation and grid connection
The planning assessment models 1,120 MWp of solar modules before conversion to AC, and compares this with a theoretical maximum of 800 MW AC exported to the grid.
Developer estimates suggest around 1,125,600 MWh (1.13 TWh) of annual electricity output if built and operating as projected, equivalent to the estimated annual electricity use of around 400,000 typical UK households. These are forecasts, not delivered power or measured generation.
The planned transmission connection includes on-site substations, underground cabling and works at National Grid's existing Staythorpe substation. The solar development and batteries form a single project with common grid infrastructure.
Battery storage
A planning assessment modelled a 440 MW battery capable of sustaining output for two hours, equivalent to 880 MWh. The assessment describes this as an illustrative configuration; the final storage capacity may differ.
Land use and site arrangement
The consented site covers approximately 1,765 hectares, including about 1,025 hectares allocated to solar development. The remaining land includes mitigation and habitat enhancement, underground cabling and access.[3]
The development comprises groups of land parcels near Caunton, Ossington, Norwell and surrounding villages. The developer’s site includes an overview masterplan of the proposed solar park and grid connection.
Biodiversity and public access
Elements Green proposes planting approximately 64,500 trees and more than 50 kilometres of new hedgerows, with habitat creation and enhancement work across areas outside the main solar fields. It also envisages 28 new public-access permissive paths and bridleways, totalling around 34.8 kilometres.
Why it matters
The consent authorises one of Britain's largest planned solar generation projects and a substantial co-located storage installation. If built, the solar farm would add hundreds of megawatts of homegrown renewable electricity capacity and give the grid additional flexibility through battery storage, using an established national electricity connection at Staythorpe.
Timeline
2024
Early public consultation on the emerging solar scheme.
27 June 2025
Elements Green Trent Limited submits the DCO application.
22 July 2025
Planning Inspectorate accepts the application for examination.
26 November 2025 – 28 April 2026
Statutory examination takes place.
28 July 2026
Examining Authority submits its recommendation to the Energy Secretary.
27 October 2026
The Department for Energy Security and Net Zero grants development consent.
2027 (indicative)
Developer's earlier target for construction commencement; actual start not yet confirmed.
Latest developments
The government has granted development consent for the Great North Road Solar and Biodiversity Park, an 800 MW solar generation project proposed north-west of Newark in Nottinghamshire.
Developed by Elements Green, the scheme would combine solar panels, battery energy storage and a new grid connection to the existing Staythorpe substation. The planning assessment modelled a 440 MW / 880 MWh battery as an illustrative configuration, alongside land for habitats, tree planting and public access.
The development covers approximately 1,765 hectares across multiple land parcels, of which around 1,025 hectares are designated for solar development. Elements Green estimates that the completed solar farm could generate around 1.13 TWh of electricity a year, equivalent to the annual use of approximately 400,000 homes.
The consent follows a national infrastructure examination completed in April 2026. Construction has been provisionally envisaged from 2027; the solar farm and batteries are not yet built or generating electricity.
Sources
- gov.uk ↗
- nsip-documents.planninginspectorate.gov.uk ↗
- gnrsolarpark.co.uk ↗
- renews.biz ↗
- gnrsolarpark.co.uk ↗
- gnrsolarpark.co.uk ↗
- elementsgreen.com ↗
- renewablesnow.com ↗
- westbridgfordwire.com ↗
- gov.uk ↗
- nsip-documents.planninginspectorate.gov.uk ↗