Hanger Lane ultra-rapid EV charging hub

Fastned and Places for London are building a 36-bay ultra-rapid electric-vehicle charging hub near Hanger Lane in west London. The development will provide charging for cars, taxis, vans and local commercial fleets beside the North Circular and Park Royal industrial area. Ealing Council's planning approval was announced on 18 May 2026; construction was reported under way by 27 November 2026. The partners expect the hub to open in spring 2027.[1][2]

Existing Fastned charge hub at Redbridge Park & Ride, Oxford, illustrating the operator’s canopy design
Photo creditMr Ignavy (as credited on Commons; current Geograph source uses Mr Addlepated) / Geograph Britain and Ireland; display may crop · CC BY-SA 2.0 · Fastned - Redbridge Park & Ride - geograph.org.uk - 7736454

Charging and driver facilities

The design provides space for 36 vehicles to charge at the same time, using ultra-rapid technology rated at up to 400 kW. Charging performance depends on the vehicle and conditions. The plans include yellow solar canopies, a shop, toilets and outdoor seating, with accessible bays, clear circulation routes, lighting and CCTV. The operator says the hub will use renewable electricity. The scheme's 36 bays describe the number of vehicles it can accommodate; they do not establish the grid connection's aggregate power.

Why it matters

Fastned describes the development as London's largest dedicated ultra-rapid EV charging hub. The 36-bay site is a substantial installation even against some of Britain's largest charging locations: GRIDSERVE's expanded Moto Exeter super hub has 48 ultra-rapid bays, including four for electric heavy goods vehicles. Hanger Lane's location beside the North Circular and one of London's principal industrial districts means it will serve through traffic as well as local residents, taxis and commercial fleets. The 400 kW rating also provides scope for shorter charging stops for compatible vehicles.

Delivery and wider programme

The project forms part of the Fastned–Places for London joint venture. The wider partnership aims to develop 25 London hubs by 2030. Its other sites have different delivery stages and capacities; these ambitions do not change Hanger Lane's 36-bay scope. Site work is progressing towards the forecast spring 2027 opening.

Map information

Representative site pin from Places for London’s Hanger Lane project page.

Timeline

18 May 2026
operator publicly announces Ealing planning approval.[3]

By 27 November 2026
construction confirmed continuing; actual commencement date not assigned.

Spring 2027(expected)
planned opening.

Sources
  1. fastnedcharging.com ↗
  2. placesforlondon.co.uk ↗
  3. transportandenergy.com ↗
  4. fastnedcharging.com ↗
  5. fastnedcharging.com ↗
  6. fastnedcharging.com ↗
  7. infrastructure-now.co.uk ↗
  8. thekensingtonpost.co.uk ↗
  9. zapmap.com ↗
  10. gridserve.com ↗
  11. content.tfl.gov.uk ↗