Project facts
Location: London Underground network
Delivery organisations: Transport for London and Boldyn Networks
Category: Critical Infrastructure — Telecommunications
Status: Live — phased rollout under way
Coverage: About 70% of below-ground Tube stations, October 2026
Target: Network-wide availability by the end of 2026 (TfL forecast)
Infrastructure being installed
The programme equips stations and tunnels with antennae, radio systems and cabling connected to above-ground network equipment. Sharing this infrastructure reduces the need for each operator to install its own equipment throughout the tightly constrained Underground network.
Engineers have undertaken much of the installation during short overnight engineering windows while daytime passenger services continued. Tunnels require radio-frequency cabling or dedicated coverage systems, while larger stations need more complex equipment configurations.
The rollout is built to support future emergency-services connectivity as well as passenger mobile use. Its technical readiness should not be confused with the Emergency Services Network being fully commissioned.
Coverage and new sections
TfL reported approximately 60% of stations below ground had mobile coverage in June 2026. By October, that had risen to around 70%. This is a measure of the share of underground stations, not the proportion of tunnel length covered; individual corridors and platforms may still have gaps.
Newly reported connections include substantial further stretches of the Bakerloo line between Queen's Park and Baker Street and between Piccadilly Circus and Lambeth North, subject to a Waterloo exception; and Northern line coverage between East Finchley/Hampstead and Waterloo on the Charing Cross branch, together with Borough to Morden except Elephant & Castle.
Further recent activations include Victoria line stations at Walthamstow Central, Blackhorse Road and Highbury & Islington, sections around Sloane Square and Victoria, Moorgate and Aldgate East on the sub-surface lines, and connectivity between Moorgate and Liverpool Street. Exact station and tunnel availability is maintained in TfL's published coverage list and mobile network map.
Why it matters
The programme is delivering shared mobile telecommunications infrastructure inside one of the world's oldest underground railway networks. Passengers can increasingly use ordinary 4G/5G services and obtain live transport information while travelling below ground. The equipment also lays foundations for more resilient communications serving transport operations and emergency responders.
Timeline
June 2021
TfL awards a 20-year Underground mobile-connectivity concession, subsequently operated by Boldyn Networks.
July 2024
TfL reports around 30% of below-ground Tube stations with mobile coverage. A separate report of nearly 70% of ALL Tube stations including those above ground is not a comparable measure.
11 June 2026
TfL reports roughly 60% of stations below ground connected.
15 October 2026
City Hall first publicly confirms the roughly 70% Underground coverage milestone.
26 October 2026
ianVisits reports additional sections and exceptions based on TfL's updated line-by-line coverage listing.
End of 2026 (target)
Full Underground network coverage, not yet independently verified.
Latest developments
Around 70% of London Underground stations located below ground now have a mobile signal, according to Transport for London and City Hall, as the installation of 4G and 5G equipment across the network continues.
Coverage was around 60% of below-ground stations in June 2026. New and recently activated sections include longer stretches of the Northern and Bakerloo lines, with additional coverage on the Victoria, District, Circle and Metropolitan lines. The rollout lets passengers make calls, send messages and use mobile data at an increasing number of stations and in connecting tunnels.
Boldyn Networks is delivering the shared infrastructure under a long-term agreement with TfL, with EE, Three, Vodafone and Virgin Media O2 participating. Work continues towards TfL's target of covering the Underground network by the end of 2026.