Norfolk Vanguard West Offshore Wind Farm

Norfolk Vanguard West is a planned 1.4 GW offshore wind farm being developed by RWE and KKR in the North Sea off Norfolk. It is being delivered alongside the separate 1.4 GW Norfolk Vanguard East project. Onshore cable and substation work is under way; offshore construction is expected to begin in early 2027.[1][2][3][4][5]

Financing and electricity price

RWE and KKR completed their joint venture and financing for the two wind farms in November 2026. The approximately £12 billion investment is supported by 35 international banks and includes a £1 billion National Wealth Fund commitment. Each project secured a 20-year inflation-indexed Contract for Difference in Allocation Round 7 on 14 January 2026, at a strike price of £91.20 per MWh in 2024 prices.

Delivery

Both projects are expected to be fully commissioned in 2030. Together they are expected to generate electricity equivalent to the annual needs of around three million UK homes.

Map information

The pin is an approximate representative point within the offshore West project area, not a specific turbine location.

Timeline

14 January 2026
Contract for Difference awarded.

11 November 2026
RWE and KKR announce financial close for the two wind farms.

Early 2027
Offshore construction expected to begin.

2030
Full commissioning expected.

Latest developments

Renewables & Energy · 11 November 2026

£12bn financing secured for two major Norfolk offshore wind farms

RWE and KKR have completed financing arrangements for Norfolk Vanguard East and West, two offshore wind farms with a combined planned capacity of 2.8GW. The £12bn investment includes equity from both partners and financing from 35 banks, including a £1bn National Wealth Fund commitment.

Both wind farms secured 20-year inflation-indexed Contracts for Difference in January 2026 at an agreed electricity strike price of £91.20 per megawatt-hour (2024 prices). Each project is planned 50–80km off Norfolk; onshore cables and substations are already under construction, while offshore work is expected to begin in early 2027. Full commissioning of both projects is expected in 2030. Together they are expected to generate electricity equivalent to the needs of around three million UK homes.