Piccadilly Line Upgrade

The Piccadilly Line Upgrade replaces 86 existing trains with 94 new trains and adapts depots, power supplies and platforms for them. First passenger service remains ahead.[1]

Current position

Four trains are undergoing London integration testing. They are not in passenger service; first service is forecast between December 2026 and June 2027.

Delivered and outstanding

  • Delivered: four London test trains had accumulated almost 9,000km and full route clearance by the October 2026 report.
  • Outstanding: passenger introduction, fleet rollout and supporting infrastructure. Walk-through carriages and air conditioning are planned fleet features.
[2]

Timeline

October 2024
First train arrived in London for testing.

October 2026 report
Four test trains, almost 9,000km and full route clearance recorded.