Renewables & Energy · Battery storage
SSE Monk Fryston battery storage
SSE’s 320MW / 640MWh battery south of the Monk Fryston electricity substation, on land east of Rawfield Lane. Construction and commissioning are phased; a whole-site commercial-operation date is not inferred. Consent 2021/0789/FULM was allowed on appeal APP/N2739/W/22/3300623. The separate neighbouring 2021/0633/FULM battery is not included.[1][2][3]
Benefits
- 2021/0789/FULM; owner’s published project map, south of the substation by Rawfield Lane/Fairburn. Use the battery parcel, not the substation centroid.