Teesworks — The Foundry Data Centre Campus
A large data-centre campus is planned at The Foundry, within the Teesworks industrial redevelopment estate on the former Redcar steelworks site. The proposed development will reuse previously industrial land for extensive computing and digital infrastructure.[1][2]
Current position
The data-centre campus has reserved-matters approval. A land agreement for the separately proposed Tees Dock Substation was reported in November 2026; the substation remains subject to planning approval.
Overview
Redcar and Cleveland Borough Council granted reserved-matters approval on 1 August 2025 under application R/2025/0382/ESM, following an earlier outline planning permission. Teesworks Ltd is promoting the scheme, which South Tees Development Corporation describes as approximately 5.5 million square feet of planned data-centre development.
The development
Plans cover a substantial campus of data halls, associated offices, electrical infrastructure, battery facilities, access roads and supporting works. Its location on an established industrial estate offers proximity to port, road, electricity and other utility infrastructure.
The development forms part of the wider Teesworks industrial redevelopment, which is repurposing former steelmaking land for manufacturing, energy and digital industries. Teesworks has continued discussions with prospective data-centre occupants, while a publicly confirmed final operator and construction programme have yet to be announced.[5]
Electricity infrastructure
National Grid is advancing a separate proposed 400 kV electricity substation at Dorman Point, within the Teesworks estate. Called Tees Dock Substation, the scheme is intended to provide more than 1 GW of contracted import and export connection capacity to serve industrial demand, a planned private-wire network, a data centre and energy storage.[6][3]
National Grid agreed a land transaction covering more than 70 acres at Dorman Point, as reported on 1 November 2026. The company submitted its own outline planning application in September 2026 and anticipates work from late 2027, subject to approvals. This infrastructure would support the development of large electricity users within Teesworks, including the proposed data-centre campus.[4]
Significance
The planning approval makes available a large industrial brownfield site for future digital infrastructure investment. The associated electricity network proposals could enable extensive data-processing capacity on Teesside, adding to the region's developing industrial and energy infrastructure.
Timeline
1 August 2025 — Data-centre planning approval
Redcar and Cleveland Borough Council grants reserved-matters permission under R/2025/0382/ESM for the Teesworks campus.
September 2026 — Grid substation application submitted
National Grid files the separate outline application R/2026/0711/OOM for a 400 kV Tees Dock Substation at Dorman Point.
1 November 2026 — Grid substation land agreement reported
Sky News reports an agreement for National Grid to acquire more than 70 acres at Dorman Point for the proposed new electricity infrastructure.
Spring 2027 — Further substation consultation expected
National Grid plans consultation on the detailed design, ahead of later reserved-matters submissions.
From late 2027 — Substation construction envisaged
Site remediation and construction may begin, subject to planning permission and completion of enabling work. No date is yet established for first operation of the data-centre campus.