Facilities And Connections
The station will have two wider platforms, an accessible footbridge and lifts, space for 100 bicycles, electric-vehicle charging and better connections with local bus, walking and cycling routes. It forms part of the wider Waterbeach transport plan alongside a proposed busway, travel hub and Greenway. Waiting room, toilet and café proposals are additional enhancements, not facilities confirmed as fully funded and completed.
Investment
The Greater Cambridge Partnership's project information gives a total relocation budget of approximately £37 million, financed through £20 million from the partnership and the balance of £17 million arranged with Homes England and development contributions. The £28 million construction element awarded to Spencer Rail Engineering is part of the whole, not additional.
Delivery
A construction haul road was begun in 2025 and enabling earthworks were taking place by October 2026. The GCP formally celebrated commencement of the new station works on 2 November 2026, with Spencer Rail Engineering as main contractor. The operator expects construction completion in 2028, followed by testing and commissioning, before services begin.
Local Impact
The relocated station will provide step-free access and better facilities for the growing new town, but will be farther from some existing Waterbeach homes than the current station. The existing stop is to remain in service until the new station is operational. The Department for Transport will separately lead the statutory consultation process concerning closure of the old station; this is not a decision already completed.
Map information
The pin represents the archaeological survey area for the new station and associated infrastructure near Bannold Drove, not a surveyed platform entrance. The existing Waterbeach station lies further south.
Timeline
2018
Main station planning application S/0791/18/FL considered, with detailed statutory and access conditions.
28 November 2025
Site-access haul road works begin.
October 2026
Ground enabling works and earth-moving take place beside Bannold Drove.
2 November 2026
Official commencement ceremony for the new station works.
2028
Construction completion anticipated; testing, commissioning and passenger start date to be confirmed.
Latest developments
Construction has begun on a new railway station at Waterbeach, north of Cambridge, with the Greater Cambridge Partnership and Spencer Rail Engineering marking the start of the main works on 2 November. The station is being relocated northwards from its existing village location to serve the expanding Waterbeach New Town.
The development will provide two wider platforms, an accessible footbridge with lifts, 100 cycle spaces, electric vehicle charging and connections to local walking, cycling and bus services. The overall station relocation has an approximately £37 million budget, including a £28 million station construction contract, supported by the Greater Cambridge Partnership and Homes England.
Construction is expected to finish in 2028, ahead of testing and commissioning. The new station will serve a community planned to accommodate up to 11,000 homes; the existing station is to remain open until its replacement is operational, with any closure requiring a separate Department for Transport process.