Yarner Wood Sustainable Woodland Centre
Natural England is replacing the former woodland education centre at Yarner Wood on Dartmoor with a purpose-built facility designed around locally sourced timber and low-energy operation. It will accommodate school and university visits, community groups and organisations learning about the reserve’s habitats and conservation work.[1]
Project facts
Location: Yarner Wood, East Dartmoor National Nature Reserve, Devon
Status: Live — under construction
Category: Nature & Rewilding
Organisation: Natural England
Expected completion: End of 2026 (subject to delivery)
Current programme
Construction began earlier in 2026. By 30 October, the building's structural timber frame had been erected, its roof was in place and windows and exterior cladding were being fitted. The replacement centre is not yet open.
Timber from the surrounding woodland
The new centre's engineered structural beams have been made from Douglas fir grown within East Dartmoor National Nature Reserve and donated by the Woodland Trust. The timber originated from plantations on ancient woodland sites being restored from conifer plantations towards native broadleaved woodland and temperate rainforest.
The building therefore incorporates timber removed during the landscape's continuing restoration. Western red cedar cladding, also supplied by the Woodland Trust, is intended to provide a durable exterior with reduced treatment requirements.
Off-grid energy and water
The completed building is designed to operate off-grid. Solar panels will supply electricity alongside a battery system described by Natural England as approximately 30 kVA. Rainwater harvesting, supplemented where suitable by water from the adjacent stream, will support the water supply.
Heating will primarily come from a gasification boiler. Insulation is designed to keep heat demand low, and a generator will remain available during periods of limited solar generation, particularly in winter. Natural England says the building aims to approach passive-building performance, but it is not formally certified as a passive building.
Educational facilities
The centre will replace a longstanding woodland learning facility. Its planned spaces will support school groups, environmental education, reserve activities and community gatherings, making the building itself part of the demonstration of sustainable design and woodland stewardship.
Why it matters
The centre links a tangible new educational building with woodland restoration, using timber derived from the surrounding managed landscape. Off-grid energy, water recovery and insulation are intended to reduce operational demand while supporting longer-term public education about the reserve.
Map information
The replacement centre is currently shown without a map marker while the exact new-building site is verified.
Timeline
2024
Structural-timber procurement. A government contract specified engineered Douglas-fir beams using timber from the reserve. The recorded £64,904 component contract is not the complete building cost.
Earlier in 2026
Construction begins. The existing centre was cleared and the replacement building progressed through groundwork, foundations and structural works. The precise commencement date remains to be confirmed.
By 30 October 2026
Timber frame and roof in place. Natural England confirmed the structural frame had been erected and the roof installed; windows and cladding were still being fitted.
End of 2026
Completion anticipated. Natural England plans to finish work towards the end of the year, with actual opening and systems commissioning still to be confirmed.