The investment, announced in the Budget on 28 October, will support a new central pedestrian overbridge, three additional station entrances, enlarged concourse space, increased lift capacity and an extension to Platform 14. The station is also expected to receive almost 40% more ticket barriers to help reduce congestion and shorten queues.
The new entrances are intended to improve connections towards Leeds South Bank, the Dark Arches and Princes Square. Network Rail is working with construction partner BAM on the transformation, with the government targeting delivery by 2030.
More than 27 million passengers currently use the station each year, according to the Department for Transport, which forecasts nearly 12 million additional annual passengers by 2043.
The funding commitment is confirmed, but the main £303 million transformation has not yet been completed and a project-wide construction start has not been independently verified. It is distinct from the separate £46.1 million Sustainable Travel Gateway works already taking place around the station entrance.