UK Progress Atlas

Urban Development & Housing

10 Cabot Square Office Retrofit

Canary Wharf Group plans a deep retrofit of 10 Cabot Square, a 1990s office block, designed by Howells. The scheme will reuse its foundations and much of its structural frame while providing a new façade, improved interior spaces, two additional office floors and landscaped terraces. The redevelopment will increase gross building floor area by more than 7,000m² to about 88,000m².[1][2][3]

Current position

Tower Hamlets granted planning permission for the office retrofit on 30 October 2026.

Daylight, green space and workplace improvements

The existing office building has deep floorplates, a poorly lit central atrium, ageing glazing and little outdoor space. The approved design cuts back selected upper-floor areas and extends the atrium towards the façades to bring more daylight into the centre of the building. The scheme adds south-facing terraces with planting and views, atrium breakout spaces, flexible office layouts and facilities for people who cycle to work.

A replacement ribbon-window façade is designed to improve daylight and thermal performance, with projecting cills for passive summer shading and winter solar gain. The lower floors can include commercial, food, drinking-establishment and leisure uses as set out in the planning permission.

Materials, carbon and energy

Howells says the retrofit will retain 100% of the existing foundations and more than 70% of the superstructure, reducing demolition and new structural construction. Its design-stage whole-life-carbon estimate is a saving of approximately 28,000 tonnes CO₂-equivalent against a hypothetical equivalent new building.

The designers are targeting NABERS 5.5 stars and BREEAM Outstanding. The retained structural frame is capable of supporting the two rooftop floors, according to Howells.

Planning and delivery

Tower Hamlets Council records application PA/26/00133/A1 as permitted on 30 October 2026. Planning permission covers part demolition, a replacement façade, rooftop extension, terraces, lower-level commercial and leisure uses, plant, servicing, landscaping and public-realm interface works.[4]

Press reporting indicates that construction might commence in 2027; no actual start or completion date has been verified.

Timeline

22 January 2026 — Planning application validated
The full planning application is validated by Tower Hamlets Council.

27 October 2026 — Retrofit design published
Howells sets out the design and approach to reusing the existing structure.

30 October 2026 — Planning permission granted
Tower Hamlets grants full planning permission for the retrofit.

2027 — Possible construction start
Construction could begin in 2027, according to press reporting.

Latest developments

Urban Development & Housing · 30 October 2026

Canary Wharf office retrofit approved with new terraces, brighter interiors and major structural reuse

Tower Hamlets Council granted planning permission on 30 October for the transformation of 10 Cabot Square in Canary Wharf. The redevelopment will modernise the 1990s office building while retaining its foundations and most of its structure, adding two new office floors and increasing total floor area by more than 7,000m² to approximately 88,000m².

Architect Howells' design will replace the ageing façade with more energy-efficient windows, enlarge the central atrium to bring daylight into the building, and reshape the upper floors to create south-facing landscaped terraces. New breakout areas, cycle-friendly facilities and flexible offices are intended to make the building more pleasant and adaptable. The planning permission also allows new commercial and leisure uses at lower levels.

Rather than demolishing and replacing the entire block, the project will retain all its foundations and over 70% of its superstructure. Howells estimates that this could avoid approximately 28,000 tonnes of carbon dioxide-equivalent emissions compared with an equivalent new building. Construction has not yet been confirmed as started; the project's environmental and design benefits remain prospective until the retrofit is delivered.

Sources
  1. development.towerhamlets.gov.uk ↗
  2. nla.london ↗
  3. constructionenquirer.com ↗