Former gasworks and railway land beside Birkenhead town centre is being prepared for a new neighbourhood, with homes, workplaces, a school and green public spaces.
Borough Yard, previously Hind Street Urban Village, is a regeneration scheme between Birkenhead Central and Green Lane stations. Wirral Council and ION Property Developments are bringing former gasworks and railway land back into use. Public communications describe up to 1,600 homes; the council’s November 2025 project masterplan records 1,456–1,554 homes across five phases, or around 1,500, with detailed plot layouts to follow. Planned uses include a primary school, commercial premises, community facilities and green spaces.[1][2]
Borough Yard regeneration · UK Progress Atlas · Original illustration · Original image
Current position
Initial clearance has removed gas holders and redundant pipelines, with preliminary ground preparation already undertaken. On 18 November 2026, councillors authorised the £36.511 million main enabling-works contract with John Sisk & Son. Further conditions remain before the next package starts. Residential construction has not been confirmed.
Benefits
Reusing former industrial land adds housing close to Birkenhead town centre and two existing Merseyrail stations. Remediation, walking and cycling connections and the planned Dock Branch South park will help reconnect land fragmented by former industrial infrastructure.
The approved package covers remediation and engineering for the early development phases, with a walking and cycling link between Mollington Link and Hind Street and an initial Waterloo Place section of Dock Branch South. Utility relocation and drainage attenuation form part of the wider enabling programme. Later park sections, highways and flyover works require separate delivery and funding arrangements.[5][6][7][4][8][9]
Scale, funding and phasing
The £36.511 million Sisk package is part of a wider enabling programme reported at around £66 million. These figures cover preparation and infrastructure, rather than the cost of building the future homes. Around £65 million in public funding was reported by the council in November, including £5 million from Wirral Council.
The developer describes a 32-acre core and a roughly 15-year programme. Wider masterplan boundaries differ from the core site. The November 2025 masterplan records 644 homes in phases A and B; earlier material used 633. Detailed designs and remaining conditions must be settled before residential delivery. No confirmed housebuilding or first-occupancy date is assigned.
Timeline
2025 Hybrid planning consent and initial site clearance; the council subsequently approves its project masterplan in November.
18 November 2026 Council approves the £36.511m main enabling-works contract.
Wirral Council has approved a £36.5 million package of major preparatory works at Borough Yard, a former gasworks and railway site beside Birkenhead town centre where up to 1,600 homes are planned. The 18 November decision authorises the council to proceed with John Sisk & Son on ground remediation and engineering for the first phases of the scheme.
The works package also includes a new walking and cycling connection between Mollington Link and Hind Street and an initial section of the Dock Branch South linear park. The wider redevelopment, previously known as Hind Street Urban Village, envisages new homes, commercial premises, a primary school and green public spaces, reconnecting the area around Birkenhead Central station with the town centre.
Outline permission for the homes was secured in 2025 and some site clearance has already taken place. The latest decision advances the substantial infrastructure needed before housebuilding can begin; it is not the start of construction on all 1,600 homes. Certain planning and contract conditions remain to be completed before the next enabling works begin.