Brockloch Forest / Bank and Afton Woodland Creation

True North Real Asset Partners is establishing a large commercial-and-native woodland scheme at Brockloch, formerly known as Bank and Afton, on former opencast coal land west of New Cumnock in East Ayrshire. The project received woodland-creation approval in June 2026 and moved into physical ground preparation by October 2026. Tree planting was expected to start in early November and be completed by March 2027. These are schedules, not verified completed hectares.[1][2][3][4][5][6]

Woodland Design

The scheme covers approximately 493 hectares, comprising about 446.5 hectares designated for planting and 46.3 hectares retained as open ground. Its detailed land allocation is 303.7ha Sitka spruce (61.6% of entire scheme), 15.9ha Douglas fir (3.2%), 11.6ha Norway spruce (2.3%), 7.6ha noble fir (1.5%), 5.3ha Pacific silver fir (1.1%), 4.5ha Scots pine (0.9%), 97.9ha native mixed broadleaves (19.9%) and 46.3ha open ground (9.3%). The individual figures total 492.8ha because the published scheme area and percentages are rounded. Sitka and the remaining conifers are intended partly for managed timber production, while broadleaves and open spaces provide habitat variation.

Restoring Former Mine Land

Approximately 100 hectares of the lower ground were formerly used for opencast coal extraction. Reshaped mine spoil and boulder landforms remain as part of the post-mining landscape; the forestry design proposes planting around these features. The comparatively sheltered and fertile lower slopes allow a greater variety of commercially productive tree species than the exposed uplands. Land restoration and tree establishment are distinct: mining reclamation predates the current forest establishment and is not proof that the new forest has already grown.

Delivery And Ownership

True North bought the Bank and Afton land in 2021. A 2025 Scottish Government environmental-information response identified Bank and Afton under Scottish Forestry pre-application reference WCP-139 at OS grid NS594105. The 493-hectare forest was reportedly granted final woodland-creation approval in June 2026. The landowner and forestry delivery advisers reported work to prepare the ground under way by 29 October 2026. Initial planting was scheduled for early November, with completion targeted in March 2027. The total capital outlay and ultimate planting density have not been disclosed.

Distinction From Enoch Hill Wind Farm

The highest land was considered unsuitable for planting. True North participated in the neighbouring Enoch Hill wind-farm landholding and subsequently sold 174.46 hectares of upland subject to a long-term lease to RWE. The wind-farm parcel is separate from the 493-hectare woodland scheme.

Ecological And Commercial Outcomes

True North expects the forest to generate future timber, sequester carbon and support habitat creation. Those outcomes are prospective and depend on survival and long-term management. Around three-fifths of the project area will be planted with Sitka spruce; only about one-fifth is allocated to native mixed broadleaves. The scheme is therefore best described as productive forestry combined with native woodland and retained open ground, not uniformly native rewilding.

Map information

The pin represents the Bank and Afton woodland pre-application site reference, to approximately 100 metres; it is not a surveyed boundary or planting-block centroid.

Timeline

2021
True North acquires the Bank and Afton/Brockloch landholding.

2025
Scottish Forestry's official pre-application register response identifies Bank and Afton as WCP-139, grid NS594105; separate forest-road access decision 14 February 2025 (East Ayrshire 24/0420/PP), not the final woodland consent.

June 2026
493-hectare woodland-creation project receives approval, according to the 29 October owner-based press report.

By 29 October 2026
Forestry ground-preparation work underway.

Early November 2026
Initial tree planting expected (not independently verified).

March 2027
Planting completion targeted; not yet achieved.

Latest developments

Nature & Rewilding · 29 October 2026

Groundworks begin on 493-hectare forest project at former Ayrshire coal mine

Work is under way to turn former opencast mining land at Brockloch, west of New Cumnock in East Ayrshire, into a new forest. Landowner True North Real Asset Partners received forestry approval in June 2026 and had begun ground preparation by 29 October, ahead of tree planting planned to start in early November. The company expects planting to finish by March 2027.

The 493-hectare forestry scheme, formerly known as Bank and Afton, allocates approximately 446.5 hectares to trees and 46.3 hectares to retained open ground. Sitka spruce accounts for 303.7 hectares (61.6% of the total area), with 97.9 hectares (19.9%) designated as native mixed broadleaves. The remaining conifer mix comprises Douglas fir (15.9ha), Norway spruce (11.6ha), noble fir (7.6ha), Pacific silver fir (5.3ha) and Scots pine (4.5ha). It is therefore a mixed productive-forestry and native-woodland project, not 493 hectares of entirely native trees.

Around 100 hectares of the sheltered lower slopes were previously used for opencast coal extraction. Some restored spoil and boulder formations remain and will be incorporated into the planting landscape. True North says the project aims to produce future timber, sequester carbon and improve biodiversity, although these results depend on successful woodland establishment.

True North separately sold 174.46 hectares of high ground associated with the Enoch Hill wind farm, subject to a long-term RWE lease. That land transaction is distinct from the Brockloch forest-creation programme. The physical-groundworks milestone was reported on 29 October 2026; actual tree planting had not yet been independently confirmed at that date.