Fife Railway Electrification and Battery-Electric Trains

Fife's railway network is undergoing a programme of civil engineering and electrification preparation to support the introduction of battery-electric passenger trains and reduce reliance on diesel. The Scottish Government-backed project will adapt infrastructure across approximately 118 kilometres of railway, incorporating overhead electrical systems, bridge renewals, track modifications and signalling changes.[1]

Current position

Network Rail reported completion of the 10–27 October engineering blockade, including bridge beams, overhead-line foundations and signalling changes. Bridge reconstruction and the wider electrification programme continue.

Project facts

Location: Fife, Scotland

Programme: Railway electrification, station/bridge engineering and future new trains

Scale: Around 118 kilometres of rail routes

Investment: £311.5 million programme figure reported in 2026

Status: Live — engineering works under way

Current programme

The improvements are designed to enable electric operation on suitable sections and battery-powered operation elsewhere, alongside capacity, reliability and accessibility benefits. Engineering work continues across the network.

Physical infrastructure work

Network Rail's programme requires height clearance for overhead electrical equipment, involving replacement or alteration of bridges over the railway and installation of foundations for overhead-line masts.

During railway closures from 10 to 27 October 2026, the old road bridges at Bennochy Road in Kirkcaldy, Muriespot near Coaltown of Balgonie and Main Street in Thornton were demolished. Rebuilding began at increased heights to make room for overhead equipment; the road bridges remained under reconstruction after the rail closure. Teams also worked on track, signalling and foundations for overhead-line masts.

Eighteen-day engineering delivery in October 2026

Network Rail closed successive sections of the Fife Circle between 10 and 27 October 2026 to undertake multiple bridge, power-line, signalling and lineside tasks during one concentrated period, with teams working continuously.

On 29 October, Network Rail confirmed that crews had installed 29 concrete bridge beams, more than 200 foundations for overhead-wire equipment, 20 steel structures and four further masts on the Leven line. Around Burntisland, 26 signalling components were replaced; teams also upgraded equipment between North Queensferry and Kirkcaldy, altered platforms at Cardenden and cleared over 209,000 m² of lineside vegetation.

Network Rail estimates the same package could have taken up to six months using intermittent weekend closures.

Thornton Main Street bridge

The Thornton bridge is being replaced to create the space needed for railway electrification. Utility-diversion and early road restrictions began on 20 June 2026. The full road closure and substantial Phase Two replacement works began on 19 October, with the railway affected between 24 and 28 October to allow removal of the old bridge and installation of new structural elements.[2][3]

The work includes diversion and reinstatement of services carried across the bridge, temporary pedestrian access and road-diversion arrangements. Network Rail's programme aims to reopen one road lane on 31 March 2027 and complete road reinstatement by 9 July 2027. Those remain forecasts, not achieved stages.

Future train services

The associated fleet programme is intended to introduce battery-electric trains on Fife routes, reducing diesel use. Delivery and entry-to-service dates remain to be confirmed.

Why it matters

Fife's programme is making physical changes needed to operate newer electric and battery-electric trains on a historically diesel-served regional network. Bridge reconstruction and overhead-line work represent durable rail infrastructure improvement, while the intended replacement fleet could reduce diesel operation and improve the service passenger experience.

Timeline

2025
Scottish Government announces broader investment in Fife railway modernisation; initial funding descriptions differ in scope from the 2026 £311.5m operator figure.

20 June 2026
Thornton Phase One road restrictions and utility diversions begin.

10–27 October 2026
Network Rail carries out an intensive 18-day sequence of railway closures for bridge, overhead-line preparation, track and signalling works.

19 October 2026
Thornton full Main Street road closure commences for major bridge replacement.

24–28 October 2026
Planned Thornton rail-line possession for demolition and installation of new structural elements; continuing road-bridge reconstruction and reopening remain future work.

29 October 2026
Network Rail confirms the 18-day engineering blockade outcomes: 29 concrete bridge beams, over 200 overhead-line foundations, 20 steel structures, four Leven-line masts, 26 signalling components and extensive lineside works.

31 March 2027 (target)
One lane of Thornton Main Street reopened.

9 July 2027 (target)
Thornton road bridge project completes.

Future
Energisation, battery-electric train deliveries and entry to service, awaiting confirmed official milestones.

Latest developments

Transport · 19 October 2026

Major bridge replacement phase begins on Fife railway electrification scheme

A major phase of work has begun at Thornton in Fife as Network Rail replaces a road bridge over the railway to create clearance for future overhead electrical equipment. Main Street closed to road traffic on 19 October for the next phase of reconstruction, following earlier utility-diversion works which started in June. The rail line was scheduled to close during 24–28 October for demolition and installation of the replacement bridge structure, with road access due to be restored in stages during 2027. The work forms part of the Scottish Government's £311.5 million Fife rail modernisation programme, which includes electrification works across 118 kilometres of railway and the future introduction of battery-electric trains. Other October works include bridge changes around Kirkcaldy and Coaltown of Balgonie, overhead-line foundations, track changes and signalling upgrades.

Transport · 27 October 2026

Fife railway engineers complete months of planned upgrades in 18-day closure

Network Rail has completed a concentrated programme of bridge, electrification and signalling work across Fife in 18 days, delivering tasks that it estimates would otherwise have required up to six months of intermittent weekend railway closures.

Sections of the Fife Circle were closed from 10 to 27 October while engineers worked around the clock. The old road bridges at Bennochy Road in Kirkcaldy, Muriespot near Coaltown of Balgonie and Main Street in Thornton were demolished, and work began to rebuild them at a greater height to accommodate overhead electric wires.

Across the programme, teams installed 29 concrete bridge beams, more than 200 foundations for overhead-line equipment and 20 steel structures, alongside four new masts on the Leven line. They also replaced 26 older signalling components around Burntisland, modified platforms at Cardenden and cleared more than 209,000 square metres of lineside vegetation.

Network Rail said that undertaking these jobs in one continuous closure avoided returning to the railway over successive weekends. The six-month comparison describes the likely period over which intermittent closures would have been spread, not six months of continuous labour compressed into 18 days.

The work advances the £311.5 million programme to electrify approximately 118 kilometres of railway in Fife and prepare for battery-electric passenger trains. The wider electrification and bridge reconstructions remain under way; the new trains have not yet entered service.

Sources
  1. networkrailmediacentre.co.uk ↗
  2. fife.gov.uk ↗
  3. scotlandsrailway.com ↗
  4. scottishconstructionnow.com ↗
  5. scotlandsrailway.com ↗
  6. networkrailmediacentre.co.uk ↗
  7. networkrailmediacentre.co.uk ↗
  8. projectscot.com ↗