Sections of the Fife Circle were closed from 10 to 27 October while engineers worked around the clock. The old road bridges at Bennochy Road in Kirkcaldy, Muriespot near Coaltown of Balgonie and Main Street in Thornton were demolished, and work began to rebuild them at a greater height to accommodate overhead electric wires.
Across the programme, teams installed 29 concrete bridge beams, more than 200 foundations for overhead-line equipment and 20 steel structures, alongside four new masts on the Leven line. They also replaced 26 older signalling components around Burntisland, modified platforms at Cardenden and cleared more than 209,000 square metres of lineside vegetation.
Network Rail said that undertaking these jobs in one continuous closure avoided returning to the railway over successive weekends. The six-month comparison describes the likely period over which intermittent closures would have been spread, not six months of continuous labour compressed into 18 days.
The work advances the £311.5 million programme to electrify approximately 118 kilometres of railway in Fife and prepare for battery-electric passenger trains. The wider electrification and bridge reconstructions remain under way; the new trains have not yet entered service.