Current position
The council and Cruden marked the 847-home first phase as under construction in October 2026. Site preparation and infrastructure work had begun earlier in the year.
Project facts
Location: Granton, Edinburgh
Status: Live — phased redevelopment and construction under way
Planned homes: Approximately 3,500 across the wider programme
Current major phase: 847 homes
Overall programme value: £1.3 billion (reported masterplan estimate)
Lead authority: City of Edinburgh Council
Principal Phase 1 delivery partner: Cruden Group
First main phase: 847 homes
The principal current phase combines 847 new homes with 14 commercial premises, community and green spaces, new access routes and the preparation of a site for a future primary school. Its design includes homes for sale and rent, while related public-realm work is intended to provide walking and cycling connections to the surrounding district.[6][7]
The council approved Phase 1 planning permission in November 2024, confirmed its delivery business case at the end of 2025 and agreed a development partnership with Cruden in May 2026. Site preparation and infrastructure works began in June 2026; on 7 October the council, developer and Scottish Government marked the major housing construction stage as underway.
The phase includes a serviced site for a future primary school. Construction of the school is a separate stage.
Land and transport infrastructure
The council is investing in substantial enabling works across former industrial land, including site remediation, demolition or preparation of old infrastructure, connections for essential services, new roads and redesigned public areas. These works enable later housing phases and mixed-use development.
The wider programme seeks to introduce more convenient walking, wheeling and cycling routes, mobility hubs and connections with Edinburgh's transport network, including links between local residential plots and the waterfront.
Funding and investment
The National Wealth Fund publicly announced a £38.4 million financing loan to the council on 11 September 2026 to support enabling infrastructure. Council reporting indicates that the funding agreement was arranged in June, alongside the start of the first-phase site works. The loan is repayable finance, not a grant or evidence that all £38.4 million was spent in September.
The wider Granton Waterfront programme is valued at approximately £1.3 billion. A separate £142.8 million council business case covers council expenditure on enabling works and council-owned homes, rather than the full 847-home phase.
Scottish Government and City Region Deal contributions support other specified infrastructure.
Earlier projects and the wider masterplan
Separate physical work has been delivered in Granton before the Cruden-led 847-home phase, including the restoration of the former Granton Station building, completed in 2023, and housing at Granton Station View and Western Villages. The council's latest 2025–26 reporting describes Western Villages as 388 occupied homes, while construction and occupancy was progressing at Silverlea.
These accomplishments establish that the wider district has already been changing for several years. They are not evidence that the entire 3,500-home masterplan or the new 847-home phase has been completed.
The overall proposals include new cultural and business space, a low-carbon heat network, a health centre, new parks and a major coastal park, with multiple future projects and sites requiring their own delivery and planning milestones. The announced masterplan covers more than the current development plots.
Why it matters
Granton Waterfront is converting former industrial land into a residential district with roads, utilities, public space and community facilities. The current 847-home phase is under construction.
Map information
The pins mark Gasholder 1 Park and Granton Station Square, two identifiable locations within the wider regeneration. The programme covers multiple sites, including the 847-home phase around the gasholder; the pins do not trace its full extent. [2][3][4][5]
Mapped sites
Gasholder 1 Park
The restored gasholder and park sit at the heart of the wider regeneration.
Granton Station Square
The restored station and square are part of the wider regeneration.
Timeline
2020
Council approves initial Granton Waterfront Development Framework.
2022
Work begins on separate Granton Station View and Western Villages housing schemes.
2023
Former Granton Station restoration and associated square open to the public.
November 2024
Detailed planning approved for the current 847-home Phase 1.
Late 2025
Council accepts Phase 1 final business case and developer delivery arrangements.
May 2026
Development agreement with Cruden signed.
June 2026
Site enabling and land preparation begin for the major 847-home phase; NWF finance agreement concluded, according to council report.
11 September 2026
National Wealth Fund announces £38.4m loan for infrastructure.
7 October 2026
Cruden, council and Scottish Government formally mark the next major housing construction stage under way.
2033 (phase forecast)
Phase 1 completion target in project-owner published plan; actual date remains dependent on delivery.
Longer term
Further 3,500-home masterplan phases, parks and civic/commercial facilities.
Latest developments
The major next phase of Edinburgh's Granton Waterfront redevelopment is now under construction, with the City of Edinburgh Council and development partner Cruden marking progress on a scheme to create 847 homes, 14 commercial units and space for a new primary school on former industrial land. The phase forms part of a wider £1.3 billion, approximately 3,500-home regeneration programme intended to establish a new coastal neighbourhood with public spaces, cultural and leisure facilities and improved walking and cycling connections. Site preparation, remediation and infrastructure works began earlier in 2026. The National Wealth Fund announced a £38.4 million loan in September to help the council finance land remediation, new roads, utilities and public realm improvements that make later housing development possible. The council and Cruden formally marked this major construction milestone on 7 October. The remaining homes and waterfront amenities are planned across later phases and should not be described as built or fully underway.
Sources
- edinburgh.gov.uk ↗
- grantonwaterfront.com ↗
- edinburgh.gov.uk ↗
- mapcarta.com ↗
- streetlist.co.uk ↗
- umbraco-prod.nationalwealthfund.org.uk ↗
- gov.scot ↗
- scottishconstructionnow.com ↗
- cruden.co.uk ↗
- grantonwaterfront.com ↗
- grantonwaterfront.com ↗
- grantonwaterfront.com ↗
- democracy.edinburgh.gov.uk ↗
- grantonwaterfront.com ↗