No. 1 Kings — Liverpool Waterfront Regeneration First Phase
No. 1 Kings is the first approved building in the planned regeneration of the King Edward Triangle on Liverpool's northern waterfront. The 28-storey tower will provide 255 homes for rent, alongside ground-floor retail, residents' facilities and rooftop social spaces.[1][2]
Current position
The first-tower plot has been cleared and the developer expects main construction to start in mid-2027.
Overview
Liverpool City Council’s planning committee approved this first building in February 2026, subject to a legal agreement and conditions. Former buildings on its plot have since been demolished and the site cleared in preparation for construction, which the developers expect to begin in mid-2027.[5]
First-phase delivery
Designed by Brock Carmichael, No. 1 Kings is being developed by Davos Property Developments and Beetham Davos. The first phase has an estimated gross development value of £80 million and is reportedly funded by shareholders. GRAHAM was appointed as its main contractor in November 2026.
The cleared plot marks physical preparation for the approved tower, not the commencement of construction of the new building. Its main construction programme is scheduled for 2027.
Wider Kings waterfront proposals
No. 1 Kings forms part of a much larger proposed £1.2 billion regeneration of approximately eight acres of Liverpool waterfront. The masterplan envisages nine buildings accommodating further homes, office space, hotels, shops, restaurants and public spaces. A potential 70-storey hotel and residential centrepiece is among the proposed later phases.
The wider development is a proposal, not an approved construction programme: the additional buildings will require separate permissions before they can proceed.
Map information
The pin marks the approximate former Bacchus Taverna site on Waterloo Road, within the first-tower plot; it is not a surveyed building footprint. [3][4]
Timeline
February 2026 — First tower approved
Liverpool City Council’s planning committee approves the No. 1 Kings tower subject to a legal agreement and conditions.
By November 2026 — Plot cleared
Demolition and site clearance of the approved first-tower plot are complete; the precise completion date has not been established.
3 November 2026 — Main contractor appointed
GRAHAM’s appointment as main contractor is reported.
Mid-2027 — Main construction expected
The developer expects construction of the tower to begin in mid-2027.