Parc Adfer Carbon Capture Facility
Enfinium plans to install a carbon capture facility alongside the operating Parc Adfer energy-from-waste plant in Deeside, North Wales. The proposed extension would capture and compress carbon dioxide from the plant’s exhaust gases for eventual transport and storage beneath Liverpool Bay.[1][2]
Current position
Flintshire County Council issued planning permission on 4 November 2026, subject to conditions. Environmental permitting, financing and arrangements for connection to the HyNet network remain relevant to delivery; full-scale construction has not been announced.
The project
Parc Adfer has processed up to 232,000 tonnes of unrecyclable waste a year since opening in 2019, producing electricity for the North Wales Residual Waste Treatment Partnership. The proposed carbon capture extension would add approximately 21,600 square feet of plant and associated infrastructure. The development has been reported as a £200 million scheme; a 2025 economic study prepared for enfinium used an indicative £242 million capital estimate.[5][6]
Capacity and expected benefits
The environmental assessment uses a baseline of approximately 241,000 tonnes of carbon dioxide emissions a year. The proposed technology is designed to capture up to 95% of the emissions in its exhaust stream. Enfinium projects up to 120,000 tonnes a year of net carbon removals from the biogenic share of the waste, subject to capture and permanent storage. These are projected outcomes.[7][8]
Planning and delivery
After an October deferral for further consultation, Flintshire councillors backed the application on 4 November 2026 and the council’s register records an issued decision. The permission includes conditions requiring biodiversity arrangements. The committee also envisaged an agreement covering habitat improvements and long-term management.[4]
Delivery and connections
The project is intended to feed captured CO₂ into the HyNet North West network for transport to offshore geological storage. The developer says Parc Adfer has been shortlisted for connection. Its capture facility is separate from the Liverpool Bay Douglas platform; the projects would form different parts of the proposed capture-to-storage chain. Delivery and operating dates depend on future permits, funding and network arrangements.[9]
Map information
The marker represents the existing Parc Adfer industrial facility. The carbon capture plant is a proposed addition at the site; the marker does not identify the exact footprint of the new equipment. [3]
Timeline
2019 — Existing facility opens
Parc Adfer’s energy-from-waste facility begins operation.
24 October 2025 — Application submitted
Enfinium submits its application for the full-scale carbon capture plant.
7 October 2026 — Decision deferred
The planning committee defers the application for further consultation.
4 November 2026 — Planning permission issued
Flintshire’s register records the application as approved and a decision notice issued.