Project facts
Location: Former Thames Valley University campus, Slough, Berkshire[2]
Delivery partners: Muse and Homes England
Status: Approved in principle — committee resolution, subject to legal agreement
Site area: Approximately 3.6 hectares
Planned accommodation: 1,214 flats and 325 co-living rooms
Proposed scheme value: Approximately £640 million
Construction period: 2027–2037 (developer targets)
Current programme
Muse and landowner Homes England propose a new town-centre neighbourhood combining rented apartments, co-living accommodation, offices, shops, a nursery, community facilities and public green space.
On 28 October 2026, Slough Borough Council's Planning Committee resolved to grant approval for the hybrid scheme. The resolution represents a substantial planning milestone, but a formal decision notice cannot be issued until the necessary Section 106 legal agreement has been concluded.
New housing and accommodation
The scheme is described in developer announcements as providing 1,539 homes. That total combines 1,214 self-contained flats with 325 co-living rooms. The co-living component provides shared-facility accommodation.
Most of the flats are expected to be built for rent. Buildings would rise to approximately 16 storeys across the various development plots, with the detailed first phase containing five buildings ranging from 11 to 15 storeys.
The council's consideration of the hybrid application includes its assessment of the intended housing mix and financial viability. The October committee resolution does not mean that any of the proposed accommodation has been constructed or occupied.
Phase 1: detailed residential development
The first phase has been presented with detailed design information for 501 build-to-rent flats and all 325 co-living rooms, together with associated ground-floor commercial areas and landscaped space.
This phase is planned to begin during 2027, subject to the issuing of formal permission, legal requirements, procurement and physical mobilisation. Construction of this phase is projected to take about four years, but no actual start has yet been confirmed.
Phases 2 and 3: further housing and workplaces
The remaining phases are outlined rather than fully designed and will require subsequent detailed approvals and delivery decisions.
Phase 2 would provide around 331 additional flats, plus a nursery and associated car parking and support spaces, with development targeted around 2030–2034.
Phase 3 would add approximately 382 further flats and the principal office development, with the indicative programme extending from around 2034 to 2037. These later years are projections, not commitments or confirmed occupation dates.
Together, the three residential phases would produce the planned 1,214 conventional flats. The 325 co-living rooms would be delivered in the first phase.
Office, retail and community space
The commercial plans include a major office building of around 25,030 square metres and approximately 3,220 square metres of retail, leisure and other ground-floor commercial space.
The scheme also incorporates a children's nursery and a community events facility. Published documents give differing nursery dimensions and child capacities; the final specification remains unconfirmed.
Parking is planned at around 420 spaces across the site. Shops and community uses are proposed rather than leased or operating.
Streets, green spaces and connections
The plan is organised around a new central public park and landscaping between the proposed buildings. Pedestrian and cycle connections would improve routes across the former university site towards Slough station and surrounding streets.
Public play areas, social space, hard and soft landscaping and updated local road access are also included.
These spaces would create a more connected town-centre site if delivered, but neither the park nor the new paths has been completed.
Planning and legal status
The relevant application is P/03766/047, a hybrid application involving full details for the initial residential blocks and outline approval for later phases.
The Planning Committee resolved to grant permission at its meeting on 28 October 2026. The council's Chief Planning Officer is to complete and secure the Section 106 legal agreement and associated planning conditions before issuing the final decision notice.
The planning officer's recommendation set a 30 July 2027 target for completing the agreement, subject to any formally agreed extension. The resolution should therefore not be described as an unconditional, legally effective planning permission.
Development value and delivery
The estimated total project value of approximately £640 million relates to the proposed redevelopment programme. It is not a statement that £640 million has already been spent, that every phase has reached financial close or that all construction contracts have been awarded.
Muse has delivered other projects within Slough through prior local regeneration arrangements, but those completed projects, including the Curve and the ice arena, are separate from North West Quadrant.
The proposed construction programme begins in 2027 and runs through approximately 2037. Its execution will depend on legal planning completion, detailed approvals for later phases, investment and construction progress.
Why it matters
North West Quadrant would reuse a prominent cleared site beside Slough's railway station for a substantial mixed-use redevelopment, including more than 1,200 conventional flats and additional co-living accommodation, workplaces and public space.
Its present progress is a committee resolution in favour of the scheme rather than new homes physically delivered. The next milestones are formal completion of the planning agreement, building-contract mobilisation, site works, construction of the first residential buildings and eventual occupation.
Map information
The marker represents the former university redevelopment site within the council application redline. It does not show a surveyed boundary or the footprint of an individual future building. [3]
Timeline
2010
Thames Valley University closes its Slough campus.
2020–2021
Former university buildings demolished, leaving vacant redevelopment land.
2023
Homes England acquires the site from Slough Borough Council.
22 April 2026
North West Quadrant hybrid planning application submitted.
29 May 2026
Council validates application P/03766/047.
2 June 2026
Muse announces submission and opens further public engagement.
28 October 2026
Slough Planning Committee resolves to grant hybrid planning consent, subject to legal agreement and final notice.
29 October 2026
Muse and Homes England publicly confirm the committee decision.
2027 (target)
Phase 1 construction begins, subject to legal consent and mobilisation.
2030–2034 (indicative)
Phase 2 homes and related facilities.
2034–2037 (indicative)
Phase 3 remaining homes and main offices.
Latest developments
Slough Borough Council has resolved to grant planning permission for the £640 million North West Quadrant regeneration project, which would redevelop the former Thames Valley University site beside Slough railway station.
The scheme, being brought forward by Muse and Homes England, is planned to provide 1,214 new flats and 325 co-living rooms across the 3.6-hectare site, alongside approximately 25,000 square metres of office space, shops and leisure facilities, a nursery and a central public park.
The first phase has been submitted in detail and would comprise 501 build-to-rent flats and all 325 co-living rooms. Subsequent phases would deliver the remaining housing, workplaces and other facilities, with construction currently expected to begin in 2027 and continue in stages until 2037.
Councillors voted on 28 October to support the hybrid planning application. Formal planning permission is still subject to completing the required legal agreement and issuing the council's decision notice.
The £640 million figure describes the proposed overall development, not an amount already spent or confirmation that all construction funding has been committed.
Sources
- museplaces.com ↗
- slough.moderngov.co.uk ↗
- openstreetmap.org ↗
- constructionenquirer.com ↗
- democracy.slough.gov.uk ↗
- planindex.co.uk ↗
- publicnoticeportal.uk ↗
- sloughdaily.co.uk ↗
- estatesgazette.co.uk ↗
- housingtoday.co.uk ↗
- stace.co.uk ↗