HS2 begins bulk excavation at Euston as freight trains remove construction spoil

Bulk excavation is under way for HS2's new Euston station in London, with excavated material being moved by freight train from a loading facility beside the disused Track 17.

HS2 expects up to 170,000 tonnes to be carried by rail to Bedfordshire for reuse, avoiding more than 10,000 lorry journeys through London. Around 35,000 tonnes were transported in trials between February and September 2026; a further 135,000 tonnes are planned over the next ten months. Excavation is reaching around seven metres below the site, where the new high-speed platforms will be built.