Three theatres have opened in the first phase, initially providing ear, nose and throat, breast and maxillofacial surgery. The remaining three are due to open in early 2027, when further specialties will move into the building. The centre includes a post-anaesthetic care unit and Shalford Ward, where patients can recover after shorter surgical procedures.
The building was assembled from more than 160 prefabricated modules manufactured in Hull and installed at the hospital over a two-year construction programme. Royal Surrey says charitable donations have also funded more than £3.5 million of advanced surgical equipment for the new facility.
Sources
- Royal Surrey NHS Foundation Trust — openingroyalsurrey.nhs.uk
- Royal Surrey NHS Foundation Trust — first patientroyalsurrey.nhs.uk
- Royal Surrey NHS Foundation Trust — CASIC access and facilitiesroyalsurrey.nhs.uk
- Royal Surrey NHS Foundation Trust — construction startroyalsurrey.nhs.uk
- Royal Surrey NHS Foundation Trust — construction progressroyalsurrey.nhs.uk
- MTX — module installationmtx.co.uk
- Royal Surrey Charity — equipment and centreroyalsurreycharity.org.uk
- CASIC design and access statementdocs.planning.org.uk