Battersea Power Station RestorationRestored power station opened14 October 2022Completed · Opened
Battersea Power Station viewed from the north bank of the Thames.
Battersea Power Station
Photo creditMarathon · CC BY-SA 2.0 · Original image

Urban Development & Housing

The restoration of Battersea Power Station converted the former generating building into homes, offices, shops and visitor attractions. The restored building forms the second phase of the wider Battersea estate redevelopment.

Opening of the restored generating building; development of the wider estate continues.

Project details · Map

[1]

2023

Fischer Farms — Norfolk Super FarmCompleted2023Completed · Completed

Logistics & Manufacturing

Fischer Farms operates a commercial vertical farm at Food Enterprise Park, west of Norwich. The £25 million facility grows leafy vegetables and herbs indoors using stacked cultivation systems and controlled growing conditions. The building was reported complete in 2022; the equipped farm was completed and in production in 2023.

Completed and in production in 2023; building construction was reported complete in 2022.

Project details · Map

[1] · [2] · [3]

2024

Co-op LiveOpened14 May 2024Completed · Opened
The Co-op Live arena beside a canal.
Co-op Live’s exterior and canalside, 7 April 2025
Photo creditDavid Dixon · CC BY-SA 2.0 · Canalside, Co-op Live Arena (geograph 8016445) · Resized preview; display may crop.

Heritage & Culture

Co-op Live is a purpose-built indoor music and entertainment arena on Manchester’s Etihad Campus.

Project details · Map

[1] · [2]

Glenfinnan Woodland and Habitat Restoration PilotCompletedAugust 2024Completed · Completed

Nature & Rewilding

Network Rail and Forestry and Land Scotland completed a two-year habitat-restoration pilot in the West Highlands in 2024. The £300,000 programme included woodland planting and protection of rainforest and peatland habitats.

Programme completion reported on 21 August; subsequent habitat development continues.

Project details · Map

[1]

Hawking BuildingPublic tours begin11 October 2024Completed · Opened

Heritage & Culture

The Science Museum Group’s Hawking Building at Wroughton, near Swindon, houses and cares for its science, technology and medicine collections.

The first public tours began on 11 October 2024; the collection had already been moving into the building.

Project details · Map

[1]

Material Evolution — Mevo A1 Cement FacilityOpenedDecember 2024Completed · Opened

Logistics & Manufacturing

Mevo A1 is Material Evolution’s cement production facility at the CCP Building Products site in Llay, Wrexham. Its first batch was produced in October 2024, and the company announced industrial operation in December 2024.

Project details · Map

[1]

London Institute for Healthcare EngineeringOpened2024Completed · Opened

Healthcare

The London Institute for Healthcare Engineering at St Thomas’ Hospital brings King’s College London researchers, NHS clinicians and medical technology businesses together.

King’s May 2026 account dates the opening to February 2024; its March 2024 announcement describes members beginning to take up residence. The milestone is shown at year precision.

Project details · Map

[1] · [2] · [3]

2025

Sadler’s Wells EastOpened6 February 2025Completed · Opened

Heritage & Culture

Sadler’s Wells East is a dance theatre and creative venue in Stratford’s East Bank cultural district.

Official opening by the Mayor of London; the performance programme followed.

Project details · Map

[1] · [2] · [3] · [4]

London Tideway Super SewerOpenedFebruary 2025Completed · Opened

Nature & Rewilding

Tideway is London’s new interceptor sewer beneath the Thames, designed to capture sewage that would otherwise overflow into the river.

The tunnel was fully connected and operational in February 2025.

Project details · Map

[1]

Nansledan, NewquayNewquay Strategic Route opensSpring 2025Live · Opened
Pale terraced houses on Stret Myghtern Arthur in Nansledan
Homes on Stret Myghtern Arthur, Nansledan, May 2023
Photo creditMutney / Wikimedia Commons · CC BY-SA 4.0 · Original image · Compressed preview; display may crop.

Urban Development & Housing

Nansledan is a long-term urban extension on the eastern edge of Newquay, Cornwall, developed and managed by the Duchy of Cornwall. The 540-acre (approximately 218-hectare) masterplan will ultimately accommodate around 4,000 homes including associated third-party land, alongside shops, offices, employment space, schools, neighbourhood facilities and green areas. The Duchy's own project descriptions also use a figure of around 3,700 homes for the narrower Duchy-led development; the wider masterplan includes land beyond that development.

New road, pedestrian and cycling connection through Nansledan.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Silvertown TunnelOpened7 April 2025Completed · Opened

Transport

The Silvertown road tunnel connects east London across the Thames, with new bus services and charges on both it and the Blackwall Tunnel.

Project details · Map

[1] · [2]

Southampton Semiconductor FacilityOpenedApril 2025Completed · Opened

Research & Innovation

The University of Southampton’s electron-beam lithography facility enables researchers to make exceptionally fine patterns for semiconductor and photonics research.

Project details · Map

[1] · [2] · [3]

The Ray Dolby CentreOpened9 May 2025Completed · Opened

Research & Innovation

The Ray Dolby Centre is the new home of Cambridge’s Cavendish Laboratory, bringing physics research, teaching and specialist facilities together.

The building was handed over in May 2024; the official opening followed on 9 May 2025.

Project details · Map

[1] · [2]

V&A East StorehouseOpened31 May 2025Completed · Opened

Heritage & Culture

V&A East Storehouse opens up the museum’s stored collections at Here East in Queen Elizabeth Olympic Park, east London.

Storehouse public opening; the separate V&A East Museum has a different schedule.

Project details · Map

[1] · [2]

Leeds Bradford Airport Terminal ExtensionOpened17 June 2025Completed · Opened

Transport

Leeds Bradford Airport’s new terminal extension opened to passengers on 17 June 2025 as Phase 1 of the wider £100m LBA:REGEN programme.

Project details · Map

[1]

Janet Harvey Hall Shipbuilding FacilityOpened25 June 2025Completed · Opened

Logistics & Manufacturing

BAE Systems’ Janet Harvey Hall at Govan in Glasgow is a covered shipbuilding facility for the Royal Navy’s Type 26 frigates.

Project details · Map

[1] · [2]

Auchteraw BESSCommercial operationSummer 2025Completed · Opened

Renewables & Energy

Auchteraw is Field’s grid-scale battery near Fort Augustus in the Scottish Highlands.

Commercial operation began in summer 2025, as confirmed by Field’s March 2026 announcement.

Project details · Map

[1]

Cleve Hill 373 MW Solar FarmCompleted1 July 2025Completed · Completed

Renewables & Energy

Cleve Hill is a large solar farm near Faversham on the north Kent coast, with a separately mapped energy-storage component.

Solar construction completion and full commercial operation; the separate battery phase is excluded.

Project details · Map

[1] · [2]

Springfield ParkOpened9 July 2025Completed · Opened

Nature & Rewilding

Springfield Park is a new public green space within the redevelopment around Springfield University Hospital in Tooting.

Official opening of the 32-acre park; parts had opened earlier.

Project details · Map

[1]

Isambard AI SupercomputerOpenedJuly 2025Completed · Opened

Research & Innovation

Isambard-AI is a supercomputer operated by the University of Bristol at Bristol and Bath Science Park. It is part of the UK’s AI Research Resource.

Project details · Map

[1] · [2] · [3]

Thurrock Storage 300 MW BESSEnergised and delivering powerAugust 2025Completed · Opened

Renewables & Energy

Thurrock Storage is Statera’s large battery installation in Essex, providing flexible electricity storage for the grid.

Statera reported energisation and power delivery in August 2025; the project website dates commercial operation to November 2025.

Project details · Map

[1] · [2]

British Sugar Bury St Edmunds Evaporator UpgradeCompletedSeptember 2025Completed · Completed

Logistics & Manufacturing

British Sugar completed a £19.5 million installation of new evaporators, heat exchangers and related process equipment at its Bury St Edmunds factory in September 2025. The equipment reduces the steam required to concentrate sugar during beet processing.

The evaporators were commissioned in September 2025.

Project details · Map

[1] · [2] · [3] · [4] · [5]

Google Waltham Cross Data CentreOpenedSeptember 2025Completed · Opened

Digital Infrastructure

Google’s Waltham Cross data centre provides infrastructure for its cloud, AI and consumer services in the UK.

Project details · Map

[1]

Moderna Innovation and Technology CentreOpenedSeptember 2025Completed · Opened

Healthcare

Moderna’s Innovation and Technology Centre at Harwell, Oxfordshire, combines a vaccine manufacturing facility with clinical research and development laboratories.

Project details · Map

[1] · [2]

Sheffield Hallam Howard Street campus buildingsOpenedSeptember 2025Completed · Opened

Research & Innovation

Sheffield Hallam’s Howard Street development added three city-centre buildings: Langsett, Redmires and Strines. They house teaching, research and specialist facilities for several disciplines.

The three Howard Street buildings welcomed students for the September 2025 academic intake; this does not date completion of every future campus project.

Project details · Map

[1] · [2]

Oxford Life and Mind BuildingOpenedOctober 2025Completed · Opened

Research & Innovation

Oxford’s Life and Mind Building brings biology and experimental psychology into a shared teaching and research facility.

Project details · Map

[1]

Beaulieu Park Railway StationOpened2025-10-26Completed · Opened
Platform and canopy at Beaulieu Park station.
Beaulieu Park station, 27 October 2025, the day after opening
Photo creditHJ Mitchell · CC BY 4.0 · Original image · Resized preview; display may crop.

Transport

Beaulieu Park station opened on the Great Eastern Main Line in October 2025, becoming its first new station in more than a century. Between Chelmsford and Hatfield Peverel, it serves north-east Chelmsford and the planned Chelmsford Garden Community, where the council envisages around 10,000 homes. The scheme was funded by £141 million from the government’s Housing Infrastructure Fund and £34 million from local partners and developer contributions.

Project details · Map

[1] · [2]

Manchester Airport Terminal 2 TransformationOpenedNovember 2025Completed · Opened

Transport

Manchester Airport’s Terminal 2 transformation has expanded and modernised the terminal and its passenger facilities.

The scheduled airline moves to Terminal 2 were completed in November 2025; later fit-out and separate Terminal 3 works are distinct.

Project details · Map

[1]

AESC Sunderland battery gigafactoryOpened2025Completed · Opened

Logistics & Manufacturing

AESC’s second Sunderland battery factory at the International Advanced Manufacturing Park supplies electric-vehicle batteries for Nissan.

Opening confirmed by 16 December 2025; an exact opening day is not established.

Project details · Map

[1] · [2]

Craven Cottage ExpansionOpened2025Completed · Opened

Heritage & Culture

The new Riverside Stand expands Craven Cottage with seating, hospitality and a riverside leisure destination known as Fulham Pier.

Riverside Stand and hospitality spaces opened in stages; the designer records 2025. No single day is established for all spaces.

Project details · Map

[1] · [2] · [3]

Everton StadiumOpened2025Completed · Opened
Everton Stadium during construction at Bramley-Moore Dock.
Everton Stadium during construction
Photo creditChris Morgan · CC BY-SA 2.0 · New Everton Stadium (geograph 7396627)

Heritage & Culture

Everton’s Hill Dickinson Stadium at Bramley-Moore Dock is a football and events venue on Liverpool’s waterfront.

The club received the building in December 2024; fit-out and test events preceded the first Premier League match on 24 August 2025.

Project details · Map

[1] · [2] · [3] · [4]

Lidl Belvedere Distribution Centre RedevelopmentCompleted2025Completed · Completed

Logistics & Manufacturing

Lidl has completed a £285 million redevelopment of its Belvedere distribution centre in south-east London, expanding its warehousing and grocery-distribution capacity through construction of an additional building and replacement of the original warehouse.

Lidl confirmed completion of the two-stage redevelopment in August 2025.

Project details · Map

[1] · [2] · [3] · [4]

Vantage LHR2 Data CentreOpened2025Completed · Opened

Digital Infrastructure

Vantage’s LHR2 data-centre campus in Park Royal, west London, provides computing infrastructure for cloud and AI services.

Existing 2025 opening retained. The developer's 11 September release forecast an end-September opening; subsequent reporting confirms the campus opened. No exact day is claimed.

Project details · Map

[1] · [2] · [3]

Birmingham Airport upgradesWorks programme2025–29Live · Expected

Transport

Birmingham Airport is delivering a phased programme of arrivals, baggage-handling and airfield improvements through 2029. Works include aircraft stands, taxiways, runway repairs and terminal heating and cooling systems.

Programme period, rather than a confirmed completion date for every work package.

Project details · Map

[1]

2026

Today · 24 Nov
Zenobē Kilmarnock South 300 MW BESSCommercial operation announced21 January 2026Completed · Opened

Renewables & Energy

Kilmarnock South is a grid-connected battery designed to store electricity and support a stable network as renewable generation grows.

Project details · Map

[1]

Fujifilm Biotechnologies Campus ExpansionOpened11 February 2026Completed · Opened

Healthcare

Fujifilm’s Billingham expansion adds biopharmaceutical manufacturing and process development facilities in the North East.

The opening ceremony was in February; manufacturing operations were separately targeted for the first half of 2026.

Project details · Map

[1]

Bogs & Bittern — Avalon Marshes (2024–26)Funded habitat works completedFebruary 2026Completed · Completed

Nature & Rewilding

Somerset Wildlife Trust completed wetland works at seven Avalon Marshes sites. The programme installed and repaired culverts, added an eel pass, reinforced bunds and managed reedbeds, ditches and wet grassland. Work at Brides Fields in Glastonbury included meadow establishment, tree planting and a leaky dam.

Project details · Map

[1] · [2] · [3]

Hertfordshire Chalk Rivers Restoration (2024–26)CompletedFebruary 2026Completed · Completed

Nature & Rewilding

Herts and Middlesex Wildlife Trust completed a two-year programme of river and wetland works across the Ash, Lea, Quin and Stort. Contractors and volunteers regraded banks, reconnected meanders, replenished riverbed gravels and installed woody habitat. Weir removal and changes to fords improved fish passage.

The funded programme concluded; the trust continues other catchment work.

Project details · Map

[1] · [2]

Hoo Peninsula Wetland Restoration ProgrammeFunded restoration programmeFebruary 2026Completed · Completed

Nature & Rewilding

Wetland restoration on Kent’s Hoo Peninsula formed part of the RSPB’s Species Coastal and Wetlands programme. Work with landowners improved coastal and floodplain grazing-marsh habitat for breeding waders.

Completion refers to the funded Species Coastal and Wetlands delivery programme, including its Hoo Peninsula work. It does not date completion of every installation described in the earlier site plans.

Project details · Map

[1] · [2] · [3]

Re:New Nature — New Forest (2024–26)CompletedFebruary 2026Completed · Completed

Nature & Rewilding

New Forest National Park Authority and its partners completed habitat work across 31 landholdings between March 2024 and February 2026. The programme included heathland management, woodland restoration, new and restored ponds, meadow creation and hedgerow planting.

Project details · Map

[1] · [2] · [3]

Wet Willow Wildlife (2024–26)CompletedFebruary 2026Completed · Completed

Nature & Rewilding

Lancashire Wildlife Trust and The Conservation Volunteers completed wet-woodland works across Bolton, the Salford and Wigan mosslands, Trafford and the Mersey Gateway. Work included coppicing, selective tree removal, scrub planting, invasive-species control and measures to retain water. These treatments maintain the low, dense woodland and decaying timber used by willow tits.

Project details · Map

[1] · [2]

Northumberland Park StationOpened22 February 2026Completed · Opened

Transport

Northumberland Park is a new National Rail station on the Northumberland Line, connecting the railway with the Tyne and Wear Metro.

Project details · Map

[1] · [2]

Ukrspecsystems Drone FactoryOpened25 February 2026Completed · Opened

Logistics & Manufacturing

Ukrspecsystems has opened a drone manufacturing facility in Suffolk, with associated testing and training facilities.

The MOD report published on 26 February states that the minister opened the facility the previous day.

Project details · Map

[1]

St Peter’s Church, Forncett — Heritage RestorationMajor restoration completedMarch 2026Completed · Completed

Heritage & Culture

Grade I-listed St Peter’s Church in Forncett has been restored after deterioration threatened its historic fabric. Its round tower dates from around AD 1000; much of the church was built in the later Middle Ages.

Project details · Map

[1] · [2]

Bedlington Railway StationOpened29 March 2026Completed · Opened

Transport

Bedlington station restores passenger rail access to the town through the Northumberland Line.

Project details · Map

[1] · [2]

Thanet Earth — Seventh High-Tech GlasshouseOpened2026-04Completed · Opened

Logistics & Manufacturing

Thanet Earth has completed its seventh commercial glasshouse at Birchington in Kent, expanding one of the UK's largest controlled-environment horticultural complexes. The project added 6.5 hectares of illuminated tomato-growing space to the existing site, increasing its total commercial growing area from 45 to 51.5 hectares. The new glasshouse, known as TG7, is designed to produce approximately 150 million additional tomatoes each year. Construction began in March 2025, and the first tomato harvest from the new facility took place in April 2026.

Project details · Map

[1]

Stephen A. Schwarzman Centre for the HumanitiesOpened25 April 2026Completed · Opened

Research & Innovation

Oxford’s Schwarzman Centre brings seven humanities faculties, a library and public arts spaces together in the Radcliffe Observatory Quarter.

Public opening of the Centre and cultural programme; academic occupation began in October 2025.

Project details · Map

[1] · [2]

Aldi Bardon Automated Distribution CentreOpenedMay 2026Completed · Opened

Logistics & Manufacturing

Aldi has invested more than £500 million in a large automated distribution centre at Bardon, Leicestershire, which began operations in May 2026. The 1.3 million-square-foot site adds national grocery storage and replenishment capacity, with automated handling systems for ambient, chilled and frozen goods.

First operations began in May 2026; the centre is expected to ramp up towards full capacity in 2027.

Project details · Map

[1] · [2] · [3] · [4] · [5] · [6]

Horniman Nature + LoveOutdoor spaces openingMay 2026Live · Opened

Heritage & Culture

The Horniman Museum's £12.5 million Nature + Love programme is renewing its historic natural history displays and creating new spaces for visitors to explore the natural world. It combines refurbishment of the Grade II-listed gallery with improvements to the gardens at Forest Hill.

Outdoor visitor spaces delivered through Nature + Love.

Project milestones

Project details · Map

[1] · [2]

National Breast Imaging Academy — Training CentreOpenedMay 2026Completed · Opened

Healthcare

The National Breast Imaging Academy’s purpose-built training centre is an extension to the Nightingale Centre at Wythenshawe Hospital. It opened in May 2026, providing specialist training and additional breast-clinic space.

Project details · Map

[1]

Tiptree Four-Hectare Precision Strawberry-Growing InstallationCompletedMay 2026Completed · Completed

Logistics & Manufacturing

Wilkin & Sons brought a new four-hectare protected strawberry-growing installation into production in Tiptree, Essex, in May 2026. Using Meteor Systems’ Mini-Air Pro technology, it combines automated ventilation with rainwater collection and irrigation-water recycling.

First harvest from the four-hectare installation.

Project details · Map

[1] · [2]

Canada Water MasterplanFirst phase completion9 June 2026Approved · Completed
Canada Water and the buildings surrounding the waterfront.
Canada Water waterfront and surrounding buildings, 9 March 2025; neighbourhood context
Photo creditAcabashi · CC BY-SA 4.0 · Original image · Resized preview; display may crop.

Urban Development & Housing

Canada Water is a 53-acre regeneration project around Canada Dock in Southwark, bringing homes, workplaces, shops, leisure facilities and public spaces to former retail and industrial land. British Land and AustralianSuper completed the first phase in 2026; the wider approved masterplan allows up to 4,184 homes.

British Land announced completion of the first phase with the launch of Three Deal Porters.

Project details · Map

[1] · [2] · [3]

Olympia RedevelopmentRooftop dining and public spaces15 June 2026Live · Opened

Urban Development & Housing

Olympia’s redevelopment adds hospitality and conference facilities around its historic London exhibition halls.

Opened phase; not whole-project completion.

Project milestones

Project details · Map

[1] · [2] · [3]

Olympia RedevelopmentARC music venue16 June 2026Live · Opened

Urban Development & Housing

Olympia’s redevelopment adds hospitality and conference facilities around its historic London exhibition halls.

Music venue opening; Self Esteem played the opening shows on 16–17 June.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Cambridge South StationOpened28 June 2026Completed · Opened
A train at the platform at Cambridge South station.
A train at Cambridge South station, 3 August 2026
Photo creditBailey Amiss · CC BY-SA 4.0 · Original image · Resized preview; display may crop.

Transport

Cambridge South station provides direct rail access to the Cambridge Biomedical Campus and nearby communities.

Project details · Map

[1]

Crystal Palace Park — Heritage RegenerationMain heritage and landscape works completedSummer 2026Completed · Completed

Heritage & Culture

Crystal Palace Park has completed a £22 million programme restoring its Victorian landmarks and upgrading public spaces, accessibility and visitor facilities. Delivered by Bromley Council and Crystal Palace Park Trust, it is the park's largest regeneration since the Crystal Palace was destroyed by fire in 1936.

Finishing planting and temporary terrace closures continue. The sports centre upgrade is a separate project.

Project details · Map

[1] · [2]

COMPASS Advanced Manufacturing FacilityOpened16 July 2026Completed · Opened

Research & Innovation

COMPASS is an advanced manufacturing research facility in South Yorkshire focused on producing large components from composite materials.

Project details · Map

[1]

Grosvenor Square Wildlife HavenOpenedJuly 2026Completed · Opened

Nature & Rewilding

The Grosvenor Square redesign restores and adapts the Mayfair garden square with richer planting and new spaces for people and wildlife.

Project details · Map

[1] · [2]

Holly House and Prudhoe House — Tottenham Heritage Arts HubRestored arts hub openedJuly 2026Completed · Opened

Heritage & Culture

Two adjoining historic Georgian townhouses on Tottenham High Road have been restored and brought back into active use as a permanent creative hub operated by the Sarabande Foundation, established by the late fashion designer Alexander McQueen.

Opening predates the November heritage-register update.

Project details · Map

[1] · [2] · [3] · [4]

Kynren — The Storied LandsOpened18 July 2026Completed · Opened

Heritage & Culture

The Storied Lands is Kynren’s daytime live-performance park at Bishop Auckland, County Durham, alongside its established night show.

Opening phase of the daytime park.

Project details · Map

[1] · [2]

Coalburn I 500 MW BESSOpenedAugust 2026Completed · Opened

Renewables & Energy

Coalburn 1 is a large battery-storage installation in South Lanarkshire, developed by CIP with Alcemi.

Project details · Map

[1]

ONE Eastside Tower (150m)CompletedAugust 2026Completed · Completed

Urban Development & Housing

One Eastside is a 150-metre residential tower on a former college site in central Birmingham.

Project details · Map

[1]

University of Bristol Temple Quarter Enterprise CampusOpened7 September 2026Completed · Opened

Research & Innovation

The University of Bristol’s Temple Quarter Enterprise Campus is a teaching, research and enterprise campus beside Bristol Temple Meads, focused on business and digital technologies.

Opening of the Sloane Robinson Building at the Temple Quarter campus.

Project details · Map

[1] · [2] · [3]

Corrour Research CentreOpened12 September 2026Completed · Opened

Research & Innovation

Corrour Research Centre is a residential fieldwork, teaching and collaboration base for the University of St Andrews on the Corrour estate in the Scottish Highlands.

The facility opened on 12 September 2026.

Project details · Map

[1]

Shakespeare’s Globe Research and Collections CentreOpened22 September 2026Completed · Opened

Heritage & Culture

A purpose-built library and archive centre at Shakespeare’s Globe provides public access to Shakespeare research collections.

Public reading-room access began on this date.

Project details · Map

[1] · [2]

Wandsworth Riverside Lifeboat StationOpened22 September 2026Completed · Opened

Transport

The RNLI’s Wandsworth Riverside station replaces its former Chiswick base, serving the same stretch of the Thames between Battersea and Richmond. The station occupies a refitted former sales centre and office building at Point Pleasant.

Operational relocation of the Chiswick crew to the replacement station.

Project details · Map

[1] · [2]

Vertical Aerospace Valo Assembly CentreOpened24 September 2026Completed · Opened

Logistics & Manufacturing

Vertical Aerospace’s Valo Aircraft Assembly Centre is at the company’s Flight Test Centre at Cotswold Airport, near Kemble in Gloucestershire.

Valo assembly centre at Cotswold Airport.

Project details · Map

[1] · [2]

Sandilands Nature ReserveOpened26 September 2026Completed · Opened

Nature & Rewilding

The National Trust has converted a former Lincolnshire coastal golf course into a 30-hectare wetland nature reserve and opened it to the public on 26 September 2026.

Project details · Map

[1] · [2]

Balgray StationOpened27 September 2026Completed · Opened
Balgray station seen across a grassy area from the south.
Balgray station, viewed from the south, 27 September 2026
Photo creditAlex Noble · CC0 1.0 · Original image · Resized preview; display may crop.

Transport

Balgray is a new station on the Neilston line serving south Barrhead and Dams to Darnley Country Park. Passenger services began on 27 September 2026.

Project details · Map

[1] · [2]

AMTEC Filton training campusOpened28 September 2026Completed · Opened

Research & Innovation

Weston College Group’s Advanced Manufacturing Technical Excellence College has a specialist apprentice-training campus on Airbus’ Filton site, near Bristol.

Opening of the Filton training campus.

Project details · Map

[1]

Kendrew Barracks Military Working Dog FacilitiesOpened29 September 2026Completed · Opened

Critical Infrastructure

New veterinary, rehabilitation, training and kennel facilities at Kendrew Barracks provide the home of the 1st Military Working Dog Regiment. The opened dog compound forms part of a wider £77 million investment programme at the barracks.

Official opening of the veterinary clinic and kennels; further scent-training and headquarters works have separate delivery dates.

Project details · Map

[1] · [2]

Leigh and Hildenborough Flood DefencesOpened30 September 2026Completed · Opened

Critical Infrastructure

The Environment Agency has opened the expanded Leigh flood storage area and new Hildenborough defences after a three-year construction programme.

Official opening of the expanded Leigh storage area and Hildenborough defences.

Project details · Map

[1]

Windermere Wastewater and Storm Overflow UpgradesAmbleside tank progress reported1 October 2026Live · Completed

Nature & Rewilding

United Utilities is upgrading wastewater treatment and storm overflow storage across the Windermere catchment. The programme is valued at up to £200 million and covers 15 projects: improvements at nine treatment works and additional storage at six storm overflows. Some improvements are complete and construction continues at other sites.

By 1 October the first tank had reached its full height; fitting out and the second tank remain part of the project.

Project milestones

Project details · Map

[1] · [2]

Edinburgh Palm Houses RestorationPalm Houses reopening2 October 2026Completed · Opened

Heritage & Culture

The Royal Botanic Garden Edinburgh has restored its two 19th-century Palm Houses, which shelter collections of palms, ferns and rare plants.

Reopening of the restored Palm Houses.

Project details · Map

[1]

Portsmouth Community Diagnostic Centre (Rodney Road)Opened5 October 2026Completed · Opened

Healthcare

An existing NHS building at Rodney Road has been adapted into a community diagnostic centre run through a partnership between Portsmouth Hospitals University NHS Trust and Alliance Medical. The centre is treating patients and offers MRI, CT, X-ray and ultrasound outside the acute hospital setting.

Opening date reported by Healthwatch Portsmouth in its 6 October update; individual services moved in stages.

Project details · Map

[1] · [2] · [3] · [4]

Rivan Production Base 1Opened5 October 2026Completed · Opened

Logistics & Manufacturing

Production Base 1 in South Bermondsey, London, brings Rivan’s research, assembly and testing of modular synthetic natural gas plants into one factory.

Opening of the factory.

Project details · Map

[1]

Pulpex Westway Fibre-Bottle FactoryOpened2026-10-08Completed · Opened

Logistics & Manufacturing

Pulpex opened its first commercial fibre-bottle factory at Westway in Renfrew on 8 October 2026. The plant has an initial design capacity of up to 40 million bottles a year and supports approximately 39 manufacturing jobs.

Project details · Map

[1] · [2] · [3]

North Oxfordshire Project Gigabit Full-Fibre RolloutCompleted13 October 2026Completed · Completed

Digital Infrastructure

Gigaclear has completed a new full-fibre broadband network reaching 3,880 homes and businesses across rural North Oxfordshire. The £8.2 million deployment was delivered through the UK government's Project Gigabit programme and finished four months ahead of schedule, with completion announced on 13 October 2026.

Completion announced by Building Digital UK.

Project details · Map

[1] · [2]

IonQ Quantum Innovation Centre, CambridgeOpened15 October 2026Completed · Opened

Research & Innovation

IonQ and the University of Cambridge’s quantum research centre is based at the Cavendish Laboratory’s Ray Dolby Centre in West Cambridge.

Opening of the innovation centre.

Project details · Map

[1]

Amazon Peterborough One Distribution Centre (EUK1)Opened2026-10Completed · Opened

Logistics & Manufacturing

Amazon opened its first One Distribution Centre in the UK at Peterborough in October 2026. The facility was created by permanently converting and equipping an existing industrial warehouse that had previously provided seasonal storage capacity. The centre receives goods from suppliers and distributes frequently purchased products to approximately 20 other Amazon fulfilment centres, rather than sending customer orders directly to homes.

Project details · Map

[1]

Hams Hall Battery — Phase 1350 MW first-phase commercial operationOctober 2026Completed · Completed

Renewables & Energy

Hams Hall is a major grid-scale battery storage facility in North Warwickshire, close to Birmingham. Its first phase entered commercial operation in late October 2026, providing 350 MW of power capacity and 1,243 MWh of electricity storage alongside National Grid's Hams Hall substation.

First phase entered commercial operation in late October; announced on 2 November.

Project details · Map

[1] · [2]

Tyne and Wear Metro Fleet ReplacementCompletedOctober 2026Completed · Completed

Transport

Stadler has built 46 replacement trains for Nexus, the Tyne and Wear Metro operator. The £362 million fleet programme serves the existing network across Newcastle, Gateshead, North Tyneside, South Tyneside and Sunderland.

Testing and formal acceptance of all 46 trains confirmed on 21 October; Nexus does not specify the final handover day.

Project details · Map

[1]

Cambrian Line Class 197e Fleet RenewalFirst 3 trains in passenger service19 October 2026Live · Completed

Transport

Transport for Wales is replacing Class 158 trains on the Cambrian network with Welsh-built Class 197e units. Introduction began between Machynlleth and Pwllheli, with further trains planned for the wider route.

Initial Cambrian Coast introduction between Machynlleth and Pwllheli.

Project milestones

Project details · Map

[1] · [2]

Sumitomo Electric Subsea Cable FactoryOpened19 October 2026Completed · Opened

Logistics & Manufacturing

Sumitomo Electric’s £350 million factory at the Port of Nigg is designed to manufacture high-voltage direct-current subsea cable systems for electricity transmission and offshore wind connections.

Formal factory opening; not an independently verified first-production date.

Project details · Map

[1] · [2]

RJAH Orthopaedic Hospital — New Operating TheatreFirst operation23 October 2026Completed · Opened

Healthcare

The Robert Jones and Agnes Hunt Orthopaedic Hospital near Oswestry has opened an additional specialist operating theatre, bringing its total to 14. The facility carried out its first operation on 23 October 2026.

Project details · Map

[1] · [2]

Oxford Street PedestrianisationTraffic-free phase26 October 2026Live · Opened

Urban Development & Housing

Oxford Street’s pedestrianisation programme changes road layouts and bus routes to create more space for people on foot.

Orchard Street to Great Portland Street; further streetscape improvements follow.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Siemens Chippenham Rail Technology CentreOpened6 November 2026Completed · Opened

Logistics & Manufacturing

Siemens Mobility invested £100 million in a replacement rail-technology centre combining manufacturing, digital engineering, testing and research in Chippenham. The new facility succeeds the historic neighbouring signalling works associated with railway engineering in the town since 1897. It officially opened on 6 November 2026 after construction commenced in April 2025. About 800 existing local employees transferred without a production interruption; these were existing jobs, not newly created roles. Siemens states that around 40% of its products are exported.

The new rail technology centre opened on 6 November 2026.

Project details · Map

[1] · [2] · [3] · [4] · [5] · [6] · [7]

AbbVie Oxford Research Facility ExpansionCompletion confirmedby 4 November 2026Completed · Completed

Research & Innovation

Pharmaceutical company AbbVie has expanded its Oxford research and development operations with a 12,000 sq ft laboratory, adding new capacity for work on the biology of human disease and the discovery of future medicines.

The expanded facility was announced in November 2026.

Project details · Map

[1] · [2] · [3]

Aurrigo Coventry manufacturing facilityManufacturing operationalBy 27 April 2026Completed · Completed

Logistics & Manufacturing

Aurrigo’s Power Park facility in Coventry houses its global headquarters and manufacturing operations, supporting autonomous-vehicle development, engineering and automotive production.

Aurrigo’s 27 April announcement confirms autonomous-vehicle production had already started at Power Park.

Project details · Map

[1] · [2]

Bio-Techne Bristol GMP Manufacturing FacilityCompletion confirmedby 2026-10-08Completed · Opened

Healthcare

Bio-Techne’s Bristol facility manufactures small molecules used by cell-therapy developers under Good Manufacturing Practice (GMP) standards.

Project details · Map

[1]

Chaul End Reservoir ExtensionCompletion confirmedBy summer 2026Completed · Completed

Critical Infrastructure

A new treated-water reservoir at Chaul End, near Luton, adds approximately 20 million litres of storage alongside the existing reservoir. The £10m extension is in service.

Confirmed in service during summer; no exact commissioning day is reported.

Project details · Map

[1] · [2]

Harwell Liquid Effluent Treatment Plant RemediationCompletion confirmedBy November 2026Completed · Completed

Nature & Rewilding

Nuclear Restoration Services has completed physical remediation at Harwell’s former liquid effluent treatment plant and neighbouring sewage farm, restoring 4.2 hectares of land previously used by the nuclear research site.

Physical remediation is complete; regulatory delicensing and permit surrender remain in progress.

Project details · Map

[1]

Heidelberg Materials Agecroft Recycling ExpansionCompletion confirmedby 2026-10-15Completed · Completed

Logistics & Manufacturing

Heidelberg Materials has expanded its 13-acre Agecroft recycling operation in Swinton with a new wash plant and rail siding. The wash plant can process up to 450,000 tonnes of excavated waste a year and the rail link can receive primary aggregates for the Manchester market.

Reported operational by publication date; exact commissioning day is not stated.

Project details · Map

[1] · [2] · [3]

HMP Elmley — New 247-Place HouseblockCompletion confirmedBy 9 October 2026Completed · Completed

Critical Infrastructure

A new prison accommodation block has been completed at HMP Elmley, the existing Category B/C adult men's prison on the Isle of Sheppey in Kent. The building provides 247 additional places and is part of a wider effort to increase capacity in England and Wales's prison system.

Physical construction completion confirmed by this date; first prisoner occupancy remains unconfirmed.

Project details · Map

[1]

Rushcliffe Woods AfforestationCompleted2026Completed · Completed

Nature & Rewilding

Rushcliffe Woods is a 54-acre woodland-creation site on former farmland at Upper Broughton. Rushcliffe Borough Council reported that more than 15,000 trees and shrubs had been planted by June 2026.

Council confirms more than 15,000 trees and shrubs planted by June 2026, after planting was underway in spring 2026. This dates the woodland planting milestone; habitat development continues. Only the completion year is established.

Project details · Map

[1] · [2]

Scottish Wide Area Network — Public-Sector Connectivity UpgradeCompletion confirmedby 2 November 2026Completed · Completed

Digital Infrastructure

The Scottish Wide Area Network is a nationwide communications service connecting thousands of public-sector organisations, including health services, local councils, schools and emergency services. BT completed a major transformation of the network in November 2026, upgrading connectivity at more than 5,000 sites ahead of schedule.

BT announced completion of the network upgrade on 2 November 2026.

Project details · Map

[1]

Shire Brook Valley Nature RecoveryCompletion confirmedBy March 2026Completed · Completed

Nature & Rewilding

Sheffield City Council and conservation partners completed habitat works across more than 400 acres of Shire Brook Valley in south-east Sheffield. The two-year project restored meadow and heathland, planted trees, created ponds and scrapes, and installed small dams to retain water within the valley.

Completion confirmed in the council’s 26 March report; exact finish day not specified.

Project details · Map

[1] · [2]

SSE Ferrybridge 150 MW BESSCompletion confirmedBy 20 March 2026Completed · Completed

Renewables & Energy

SSE’s Ferrybridge battery reuses the site of a former coal-fired power station in West Yorkshire to store and release electricity.

SSE reported full operation on 20 March. The release does not itself establish the exact start day.

Project details · Map

[1] · [2]

The Spark child-health centreCompletion confirmedBy 12 October 2026Completed · Opened

Healthcare

The £24 million Spark at Sheffield Olympic Legacy Park combines children’s outpatient healthcare with the National Centre for Child Health Technology.

Patient services confirmed by the Trust’s report; precise first-patient day is not specified.

Project details · Map

[1] · [2] · [3] · [4]

Tina’s Haven Nature ReserveCompleted2026Completed · Completed

Nature & Rewilding

The National Trust and Durham Heritage Coast Partnership have created a 34-hectare nature reserve on former farmland at Warren House, Horden. Initial works established woodland, wood pasture, grassland, hedgerows, ponds and wetlands, extending the coastal habitat corridor between Horden and Seaham.

Initial reserve-creation phase; exact finish date not reported.

Project details · Map

[1] · [2]

Wallasea Island bird islands and reserve expansionCompletion confirmedBy February 2026Completed · Completed

Nature & Rewilding

At Wallasea Island on the Essex coast, the RSPB is creating more space for wetland birds. Recent work has added 21 small islands to the reserve’s lagoons, while a separate land purchase has expanded the reserve by 100 hectares. The islands give birds somewhere sheltered to rest when the tide is high. The RSPB says Lapwings and Golden Plovers are already using them. They were built as part of a wider wetlands programme completed by February 2026. In January 2025, the RSPB announced that it had bought four fields at the western end of Wallasea Island. The purchase is complete, but the new habitat work has not been confirmed as under way.

Completed refers to the island works and land acquisition. The western habitat-creation phase remains planned.

Project details · Map

[1] · [2]

Wetter for Waders — Somerset Coastal WetlandsCompletion confirmedBy April 2026Completed · Completed

Nature & Rewilding

WWT and its partners completed a two-year programme of wetland works across more than 370 hectares at Steart Marshes and the neighbouring Somerset Wetlands National Nature Reserve. The work restored scrapes, ponds, lagoons and drains, improved water controls and added a saltmarsh boardwalk.

WWT reported the completed works on 9 April; this is not an exact construction finish date.

Project details · Map

[1] · [2]

Whitebirk BESSCommercial operation confirmedBy 13 March 2026Completed · Opened

Renewables & Energy

Whitebirk is Field’s grid-scale battery near Blackburn in Lancashire.

Field confirmed operation on 13 March 2026 following energisation earlier that month.

Project details · Map

[1]

Highview Carrington Liquid Air Energy StorageFirst phaseH2 2026Live · Expected

Renewables & Energy

Highview’s Carrington plant will store energy by liquefying air, then expanding it to generate electricity when required. The facility is under construction at Trafford Low Carbon Energy Park.

Forecast made in November 2025; not confirmation of full-facility operation.

Project details · Map

[1]

Jacobs Wells Baths RestorationFirst roof and fabric restoration phaseAutumn 2026Live · Expected

Heritage & Culture

Trinity Community Arts is restoring the Grade II former baths for cultural, dance and community use under a long-term lease from Bristol City Council.

Earlier forecast; completion has not been verified.

Project milestones

Project details · Map

[1] · [2] · [3]

Nscale Loughton AI CampusLoughton data centre readinessQ4 2026Live · Expected

Digital Infrastructure

Nscale’s Loughton AI Campus in Essex is being developed to host a Microsoft AI supercomputer.

Earlier Nscale target; not confirmation of operational supercomputer commissioning.

Project milestones

Project details · Map

[1] · [2]

Bristol Brabazon Railway StationCompletion / operation2026-11-23Live · Expected

Transport

A new two-platform railway station serving the Brabazon neighbourhood on the former Filton Airfield will bring passenger trains back to the Henbury Line for the first time since 1964. Construction of the initial station facilities is substantially complete, with Great Western Railway scheduled to open services on 23 November 2026.

Passenger opening scheduled; further station facilities are planned through 2028.

Project details · Map

[1] · [2] · [3] · [4] · [5]

Airbus Broughton A321 Wing LineCompletion / operationEnd of 2026Live · Expected

Logistics & Manufacturing

Airbus is converting Broughton's former A380 wing-production building into an A321 wing line.

Airbus expects conversion of the A321 wing line to finish by the end of 2026.

Project details · Map

[1] · [2]

Bridgwater tidal-barrier schemeDownstream defence earthworksEnd of 2026Live · Expected

Nature & Rewilding

A tidal barrier across the River Parrett and downstream flood defences are being built to reduce flood risk in and around Bridgwater. The scheme is designed to protect around 12,800 homes and businesses.

Main construction in the three downstream areas; barrier opening is separate.

Project milestones

Project details · Map

[1] · [2]

Cambrian Line Class 197e Fleet RenewalWider Cambrian introductionLate 2026Live · Expected

Transport

Transport for Wales is replacing Class 158 trains on the Cambrian network with Welsh-built Class 197e units. Introduction began between Machynlleth and Pwllheli, with further trains planned for the wider route.

Operator forecast for staged rollout across the wider route, with old and new trains in use during transition.

Project milestones

Project details · Map

[1] · [2]

Dogger Bank Wind Farm ASubstantially complete commissioningEnd of 2026OFF
TRACK
Live · Previous target

Renewables & Energy

Dogger Bank A is the first phase of the North Sea wind development, with 95 Haliade-X turbines rated at 13 MW each. The developer describes the phase as approximately 1.2 GW. Electricity reaches the mainland through offshore and onshore converter stations and a high-voltage direct-current transmission system.

The October government consultation reports ongoing turbine remediation, technical defects and resource constraints delaying commissioning beyond earlier forecasts.

SSE’s May 2026 forecast for substantially complete commissioning. October government consultation records continuing technical and commissioning delays.

Project details · Map

[1] · [2] · [3]

East Anglia THREE Offshore Wind FarmFull operationEnd of 2026Live · Expected

Renewables & Energy

East Anglia THREE is ScottishPower Renewables and Masdar’s 1.4 GW offshore wind project, about 69 km off Suffolk. Power will reach the National Grid through subsea export cables, a landfall at Bawdsey and an underground cable route to a converter station at Bramford.

ScottishPower’s 17 August 2026 full-operation target; foundation installation and commissioning are earlier construction milestones.

Project details · Map

[1] · [2]

Etihad Campus Development & Stadium ExpansionCompletion / operationLate 2026Live · Expected

Heritage & Culture

Manchester City’s Etihad Stadium expansion adds a larger North Stand alongside hotel, workspace and public facilities in the wider campus development.

The wider development includes workspace and public areas separately from the completed stand and opened hotel.

Project details · Map

[1] · [2] · [3]

Lansdowne Monument RestorationMain masonry repairsEnd of 2026Live · Expected

Heritage & Culture

The National Trust is conserving the Grade II* Lansdowne Monument on Cherhill Down, an obelisk built in 1845. The project repairs its damaged masonry, quoins, pointing and plinth.

The National Trust aims to complete the majority of repairs by the end of 2026, subject to weather. This is not a confirmed whole-project completion date.

Project details · Map

[1] · [2]

London Underground 4G/5G Connectivity RolloutUnderground network coverageEnd of 2026Live · Expected

Digital Infrastructure

Transport for London is introducing high-speed mobile phone connectivity throughout the London Underground, extending service across ticket halls, platforms and connecting tunnels where mobile networks previously had little or no reception. Boldyn Networks is delivering a shared underground telecommunications system under a 20-year concession awarded in 2021. The infrastructure is used by all four major UK mobile networks: EE, Three, Vodafone and Virgin Media O2. Coverage is also being introduced across other TfL networks, including parts of the Docklands Light Railway and Windrush line, as separately identified extensions.

TfL target, not a confirmed completion.

Project details · Map

[1] · [2]

Sofia Wind Farm 1400 MWCompletion / operationLate 2026Live · Expected

Renewables & Energy

RWE’s Sofia offshore wind farm is being built on Dogger Bank, with power exported to Teesside through an offshore converter and subsea cable.

Project details · Map

[1] · [2]

London Museum at SmithfieldGeneral Market permanent galleries28 November 2026Live · Expected
Dome and brickwork of the former Smithfield General Market during conversion
General Market during conversion — archive photograph, 31 March 2022
Photo creditMatt Brown; resized preview · CC BY 2.0 · Dome of the old Smithfield Market

Heritage & Culture

London Museum is moving into the former Victorian General Market at Smithfield, with the adjoining Poultry Market forming a later phase. The £437 million redevelopment reuses historic market buildings for permanent galleries, exhibition spaces, learning and collections facilities.

Unveiled on 24 November; public opening remains scheduled.

Project milestones

Project details · Map

[1] · [2] · [3]

Dalmarnock Battery Energy StorageCompletion / operation2026-12Live · Expected

Renewables & Energy

Dalmarnock is Econergy’s 40MW, 120MWh battery storage project in Glasgow. It has been connected to the grid and is being brought into commercial operation.

Forecast full commercial operation; grid connection has already occurred.

Project details · Map

[1] · [2]

Birmingham Airport upgradesWorks programme2025–29Live · Expected

Transport

Birmingham Airport is delivering a phased programme of arrivals, baggage-handling and airfield improvements through 2029. Works include aircraft stands, taxiways, runway repairs and terminal heating and cooling systems.

Programme period, rather than a confirmed completion date for every work package.

Project details · Map

[1]

Cleve Hill 150 MW BESSBattery commercial operation2026Live · Expected

Renewables & Energy

The storage component of Cleve Hill Solar Park is intended to complement the adjacent solar generation near Faversham.

Quinbrook estimates commercial operation of the 150MW / 300MWh battery in 2026. The solar farm began operating in July 2025.

Project details · Map

[1] · [2]

Leeds Bradford Airport Terminal RegenerationTwo additional security lanesEnd 2026Live · Expected

Transport

LBA:REGEN expands and refurbishes Leeds Bradford Airport’s terminal. The extension opened in 2025; refurbishment continues through later security and arrivals phases.

Airport forecast for the remaining two lanes; opening not yet confirmed.

Project milestones

Project details · Map

[1] · [2] · [3]

Lord’s Allen and Tavern stands redevelopmentAllen Stand completionWinter 2026/27Live · Expected

Heritage & Culture

MCC is redeveloping the Allen and Tavern stands at Lord’s in phases, with improved seating, spectator facilities and access.

MCC forecast for the Allen Stand; wider Tavern redevelopment follows.

Project milestones

Project details · Map

[1] · [2]

Piccadilly Line UpgradeFirst passenger serviceDecember 2026–June 2027Live · Expected

Transport

The Piccadilly Line Upgrade replaces 86 existing trains with 94 new trains and adapts depots, power supplies and platforms for them. First passenger service remains ahead.

Forecast introduction window; not whole-programme completion.

Project milestones

Project details · Map

[1] · [2]

Salford Crescent Platform UpgradeCompletion / operationLater in 2026Live · Expected

Transport

Salford Crescent station is being upgraded with a third platform, an extended footbridge and a new lift. The work also adds a canopy, seating and ticket gates. The Office of Rail and Road authorised the new infrastructure in October 2026, ahead of expected passenger use later in the year.

Expected start of passenger use, as reported by the Office of Rail and Road on 2 October 2026.

Project details · Map

[1]

Yarner Wood Sustainable Woodland CentreCompletion / operation2026Live · Expected

Nature & Rewilding

Natural England is replacing the former woodland education centre at Yarner Wood on Dartmoor with a purpose-built facility designed around locally sourced timber and low-energy operation. It will accommodate school and university visits, community groups and organisations learning about the reserve’s habitats and conservation work.

Project details · Map

[1]

2027

Horniman Nature + LoveNature Gallery and Discovery Den opening5 February 2027Live · Expected

Heritage & Culture

The Horniman Museum's £12.5 million Nature + Love programme is renewing its historic natural history displays and creating new spaces for visitors to explore the natural world. It combines refurbishment of the Grade II-listed gallery with improvements to the gardens at Forest Hill.

Announced opening date for the remaining indoor phase.

Project milestones

Project details · Map

[1] · [2]

Hornsea Project ThreeFirst powerQ1 2027Live · Expected

Renewables & Energy

Hornsea Project Three is Ørsted’s 2.9 GW offshore wind project in the Hornsea zone, approximately 120 kilometres off Norfolk.

Operator forecast, separate from full commissioning.

Project details · Map

[1] · [2] · [3]

Iceni Battery Energy StorageExpected operationQ1 2027Live · Expected

Renewables & Energy

Iceni is Ørsted’s 300MW, 600MWh battery storage project beside the Hornsea 3 onshore converter station at Swardeston, near Norwich. The two battery areas use a shared grid connection with the wind-farm infrastructure.

Operational forecast from Arenko (17 August) and Orrick (1 September); construction completion reported 20 October 2026, with commissioning continuing.

Project details · Map

[1] · [2] · [3]

Nscale Loughton AI CampusInitial GPU deliveryQ1 2027Live · Expected

Digital Infrastructure

Nscale’s Loughton AI Campus in Essex is being developed to host a Microsoft AI supercomputer.

Nscale target for delivery of the initial Microsoft GPU deployment; not a verified commissioning date.

Project milestones

Project details · Map

[1]

Bridgwater tidal-barrier schemeBarrier superstructure construction startEarly 2027Live · Expected

Nature & Rewilding

A tidal barrier across the River Parrett and downstream flood defences are being built to reduce flood risk in and around Bridgwater. The scheme is designed to protect around 12,800 homes and businesses.

Start of this construction stage.

Project milestones

Project details · Map

[1] · [2]

Royal Academy Collection Gallery redevelopmentCollection Gallery reopeningEarly 2027Live · Expected

Heritage & Culture

The Royal Academy is expanding its Collection Gallery at Burlington Gardens, restoring the sense of the original double-height hall. It is the final phase of a wider masterplan that previously restored Burlington Gardens and renovated the Academy Schools.

Project details · Map

[1] · [2] · [3]

Transpennine Route UpgradeHuddersfield main station upgradesEarly 2027Live · Expected

Transport

The Transpennine Route Upgrade is a programme of railway improvements across the approximately 70-mile Manchester–Huddersfield–Leeds–York corridor, including electrification, additional tracks, signalling, station improvements and work on bridges and level crossings.

Delivery partnership forecast for the station works.

Project milestones

Project details · Map

[1] · [2]

Blackhillock 300 MW BESSPhase 2 final commissioningH1 2027Live · Expected

Renewables & Energy

Zenobē’s Blackhillock battery near Keith stores electricity and provides grid-stability services to help absorb Scottish renewable generation.

Zenobē schedules final commissioning and grid outages for the first half of 2027, followed by full operation. The first 200 MW phase entered operation in early 2025.

Project details · Map

[1] · [2]

Bradford City VillageKirkgate external demolitionSpring 2027Live · Expected

Urban Development & Housing

City Village replaces former city-centre shopping complexes with a mixed-use neighbourhood of up to 1,000 homes, public spaces and retail and community facilities.

Forecast following internal strip-out.

Project milestones

Project details · Map

[1] · [2]

Ipswich Museum redevelopmentMuseum reopeningSpring 2027Live · Expected

Heritage & Culture

Ipswich Museum’s £12 million redevelopment restores its Victorian building on High Street and renews the galleries and visitor facilities.

Forecast museum reopening.

Project details · Map

[1] · [2]

London Museum at SmithfieldUnderground vaultsSpring 2027Live · Expected
Dome and brickwork of the former Smithfield General Market during conversion
General Market during conversion — archive photograph, 31 March 2022
Photo creditMatt Brown; resized preview · CC BY 2.0 · Dome of the old Smithfield Market

Heritage & Culture

London Museum is moving into the former Victorian General Market at Smithfield, with the adjoining Poultry Market forming a later phase. The £437 million redevelopment reuses historic market buildings for permanent galleries, exhibition spaces, learning and collections facilities.

800 square metres of public space and a free Roman London exhibition.

Project milestones

Project details · Map

[1] · [2] · [3]

New Velindre Cancer CentreCompletion / operationSpring 2027Live · Expected

Healthcare

The new Velindre Cancer Centre is being completed on the Northern Meadows in Whitchurch to provide specialist cancer care for south-east Wales.

Expected opening to patients.

Project details · Map

[1] · [2] · [3]

Numatic Somerset Manufacturing HubDistribution centre completionSpring 2027Live · Expected

Logistics & Manufacturing

Numatic International’s manufacturing hub is located on Millfield Road in Chard, Somerset. The company is expanding the site to bring together manufacturing, research, distribution and on-site energy infrastructure.

Forecast for the distribution centre only; not completion of the wider manufacturing hub.

Project details · Map

[1] · [2]

Oxford Street PedestrianisationTransitional public-space improvementsSpring 2027Live · Expected

Urban Development & Housing

Oxford Street’s pedestrianisation programme changes road layouts and bus routes to create more space for people on foot.

City Hall forecast for trees, seating and public squares; permanent design follows.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Rowett South — Bucksburn, AberdeenKinion HeightsSpring 2027Live · Expected

Urban Development & Housing

Rowett South is a major phased residential development on land associated with Aberdeen's former Rowett Institute in Bucksburn, alongside the A96 Inverurie Road. The masterplan would create around 1,700 houses and apartments, with community facilities, new green spaces and transport improvements. Development began in 2018, and by September 2026 more than 500 homes across the wider site were either complete or under construction. The latest land acquisition by Bancon Homes from the University of Aberdeen is intended to enable further phases covering approximately 1,200 homes. Those 1,200 are included within, not additional to, the masterplan's overall 1,700 homes.

Developer forecast for this 63-home phase.

Project details · Map

[1]

Sheffield Aegis Low-Carbon Transport HubCompletion / operationSpring 2027Live · Expected

Transport

Aegis Energy's Sheffield hub is a purpose-built charging and renewable-fuel site for commercial vans and trucks at Smithywood Business Park near the M1.

Planned opening of the Sheffield hub.

Project details · Map

[1]

Matrix 500 MW Eccles BESSEnergisationMay 2027Live · Expected

Renewables & Energy

Matrix Renewables’ Eccles battery is a separate Scottish Borders project from Zenobē’s nearby development.

Current developer project-calendar target.

Project milestones

Project details · Map

[1] · [2] · [3]

Birnbeck Pier RestorationCompletion / operationSummer 2027Live · Expected

Heritage & Culture

North Somerset Council is restoring the Grade II* listed Birnbeck Pier and associated buildings in Weston-super-Mare after decades of closure.

Public reopening target for the pier. Later works to island buildings and the north jetty are separate phases.

Project details · Map

[1] · [2]

Bradford City VillageFirst 97 townhouses — construction startSummer 2027Live · Expected

Urban Development & Housing

City Village replaces former city-centre shopping complexes with a mixed-use neighbourhood of up to 1,000 homes, public spaces and retail and community facilities.

Forecast start of homebuilding; no whole-programme completion date established.

Project milestones

Project details · Map

[1] · [2]

East Anglia TWO Offshore Wind FarmFirst export cable installationSummer 2027Live · Expected

Renewables & Energy

East Anglia TWO is ScottishPower Renewables’ 960MW offshore wind farm under construction in the southern North Sea, around 33km from Suffolk at its nearest point. Its export connection comes ashore north of Thorpeness.

Developer forecast for the first cable, not operation of the wind farm.

Project milestones

Project details · Map

[1] · [2] · [3]

Edinburgh Airport Terminal TransformationSouth East Pier first phaseSummer 2027Live · Expected

Transport

Edinburgh Airport's Terminal Transformation is a five-year capital programme to expand and modernise Scotland's busiest airport.

First-pier phase target; the full investment programme retains its 2031 horizon.

Project milestones

Project details · Map

[1] · [2]

Moorfields and UCL Centre for Eye HealthCompletion / operationSummer 2027Live · Expected

Healthcare

Oriel is a new centre for eye care, research and education in Camden, bringing Moorfields Eye Hospital and UCL expertise together.

Opening to patients; structural completion and ongoing fit-out are separate.

Project details · Map

[1]

Natural History Museum’s Shinfield centreBuilding completionSummer 2027Live · Expected

Heritage & Culture

The Natural History Museum’s collections, science and digitisation centre at Shinfield will bring together specimen storage, research laboratories and digitisation facilities.

Building construction target; full operation follows later.

Project milestones

Project details · Map

[1]

No. 1 Kings — Liverpool Waterfront Regeneration First PhaseMain tower construction startMid 2027Approved · Expected

Urban Development & Housing

No. 1 Kings is the first approved building in the planned regeneration of the King Edward Triangle on Liverpool's northern waterfront. The 28-storey tower will provide 255 homes for rent, alongside ground-floor retail, residents' facilities and rooftop social spaces.

Planned start of construction of No. 1 Kings; the wider masterplan requires further permissions.

Project details · Map

[1] · [2] · [3]

Staythorpe 360 MW BESSCompletion / operationMid 2027Live · Expected

Renewables & Energy

Elements Green is building a 360 MW / 720 MWh battery and 400 kV grid substation at Staythorpe in Nottinghamshire, with Mitie Power & Grid delivering construction.

The 360MW / 720MWh battery and associated grid infrastructure are scheduled to be fully operational by mid-2027.

Project details · Map

[1]

Transpennine Route Upgrade40% of route electrifiedSummer 2027Live · Expected

Transport

The Transpennine Route Upgrade is a programme of railway improvements across the approximately 70-mile Manchester–Huddersfield–Leeds–York corridor, including electrification, additional tracks, signalling, station improvements and work on bridges and level crossings.

Delivery partnership forecast published 20 August 2025; an electrification phase rather than overall programme completion.

Project milestones

Project details · Map

[1] · [2]

Thorpe Marsh 1450 MW BESSCompletion / operationQ3 2027Live · Expected

Renewables & Energy

Thorpe Marsh is a major battery project beside a former coal-power site and National Grid substation in Yorkshire.

Fidra’s commercial-operation forecast.

Project details · Map

[1]

West Park Student Residences — University of ExeterFirst accommodation phaseSeptember 2027Live · Expected

Urban Development & Housing

West Park is a major redevelopment of student housing at the University of Exeter

618 bedrooms across new and refurbished accommodation.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Hemerdon MineCompletion / operationH2 2027Live · Expected

Logistics & Manufacturing

Tungsten West is restarting the Hemerdon tungsten and tin mine at Drakelands in South Devon, using the existing mine and processing infrastructure.

Developer target for steady-state production.

Project details · Map

[1]

Lord’s Allen and Tavern stands redevelopmentTavern Stand work beginsAutumn 2027Live · Expected

Heritage & Culture

MCC is redeveloping the Allen and Tavern stands at Lord’s in phases, with improved seating, spectator facilities and access.

Intended start, subject to members’ approval.

Project milestones

Project details · Map

[1]

100 KensingtonPhased building completionsQ4 2027Live · Expected

Urban Development & Housing

100 Kensington is a 462-home development on West Cromwell Road in west London, with seven buildings arranged around a central podium garden.

Forecast completion of individual buildings.

Project milestones

Project details · Map

[1]

Matrix 500 MW Eccles BESSProject completionNovember 2027Live · Expected

Renewables & Energy

Matrix Renewables’ Eccles battery is a separate Scottish Borders project from Zenobē’s nearby development.

Current developer target; earlier financing announcement forecast Q3 commercial operation.

Project milestones

Project details · Map

[1] · [2] · [3]

UCL Institute of Neurology CampusBuilding completionNovember 2027Live · Expected

Healthcare

UCL is creating a neuroscience centre at 256 Grays Inn Road, including laboratories for the Institute of Neurology and dementia research.

UCL forecast for building completion.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Agratas Battery GigafactoryFirst battery-cell productionLate 2027Live · Expected

Logistics & Manufacturing

Agratas is building a battery-cell factory at the Gravity campus near Bridgwater, Somerset. The plant is intended to supply electric-vehicle batteries, initially for Jaguar Land Rover.

The September 2026 report retains late 2027 as the forecast for initial battery production, starting with JLR supply.

Project details · Map

[1] · [2] · [3] · [4] · [5]

Carrington 680 MW BESSGrid energisationLate 2027Live · Expected

Renewables & Energy

Carrington Storage is Statera’s 680MW, 1,360MWh battery project under construction at Trafford Low Carbon Energy Park. It is separate from Highview’s liquid-air plant and the proposed hydrogen facility.

Energisation target, distinct from full commercial operation.

Project details · Map

[1] · [2]

Energy Central InstituteInstitute openingLate 2027Live · Expected

Research & Innovation

The £25 million Energy Central Institute is being built in Blyth town centre to provide higher education, clean-energy research and skills facilities. Newcastle and Durham universities are partners in the campus.

Forecast for the institute, distinct from the already-open Energy Central Learning Hub.

Project details · Map

[1] · [2]

Twyn Hywel Energy ParkFirst electricityLate 2027Live · Expected

Renewables & Energy

Construction began at Twyn Hywel Energy Park in June 2026. The development will have up to 93.8 MW of generating capacity, with turbines reaching a maximum height of 200 metres. Bute Energy secured £160 million of project debt financing from Lloyds and Rabobank after obtaining planning consent. It is the first wind farm in the developer’s Welsh portfolio to reach construction.

Developer forecast.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Port Talbot electric arc furnace and steelworks transformationFurnace, pickle line and caster 1December 2027Live · Expected

Logistics & Manufacturing

Tata Steel plans to replace Port Talbot’s coal-based primary steelmaking with an electric arc furnace using mainly recycled steel.

Electric arc furnace, new pickle line and caster 1; further rolling-mill works follow.

Project details · Map

[1] · [2]

Windermere Wastewater and Storm Overflow UpgradesAmbleside storage completionDecember 2027Live · Expected

Nature & Rewilding

United Utilities is upgrading wastewater treatment and storm overflow storage across the Windermere catchment. The programme is valued at up to £200 million and covers 15 projects: improvements at nine treatment works and additional storage at six storm overflows. Some improvements are complete and construction continues at other sites.

Forecast for the two Ambleside storage tanks, not the whole catchment programme.

Project milestones

Project details · Map

[1] · [2]

100 KensingtonFinal build completionEnd 2027 or early 2028Live · Expected

Urban Development & Housing

100 Kensington is a 462-home development on West Cromwell Road in west London, with seven buildings arranged around a central podium garden.

The developer’s restart announcement gives early 2028 in its programme but end 2027 in a quoted timetable.

Project milestones

Project details · Map

[1]

AW 1 Uskmouth 120 MW BESSCompletion / operation2027Live · Expected

Renewables & Energy

AW1 is Ampeak’s battery project at the former Uskmouth power-station site.

Project details · Map

[1]

Awel y Môr 800 MW Wind FarmOnshore construction starts2027Approved · Expected

Renewables & Energy

Awel y Môr is an offshore wind project west of the existing Gwynt y Môr farm off north Wales.

Earliest indicative developer date, subject to FID and detailed design.

Project milestones

Project details · Map

[1] · [2]

Birmingham Airport upgradesWorks programme2025–29Live · Expected

Transport

Birmingham Airport is delivering a phased programme of arrivals, baggage-handling and airfield improvements through 2029. Works include aircraft stands, taxiways, runway repairs and terminal heating and cooling systems.

Programme period, rather than a confirmed completion date for every work package.

Project details · Map

[1]

Cambridge Cancer Research HospitalConstruction start2027Approved · Expected

Healthcare

Cambridge Cancer Research Hospital is an approved specialist hospital combining cancer treatment and research on Cambridge Biomedical Campus. The selected design provides approximately 26,000 m² of accommodation.

The hospital forecast in May 2026 that construction would begin in 2027, while preparing its full business case.

Project details · Map

[1] · [2] · [3]

Cambridge Children's HospitalMain construction start2027Approved · Expected

Healthcare

Cambridge Children’s Hospital is a proposed specialist hospital for the East of England, bringing physical and mental healthcare together with research.

The start season differs across published updates: early 2027 in the August staff FAQ, summer on the campus listing and later in the year on CUH’s page.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Coalburn 2 500 MW BESSCompletion / operation2027Live · Expected

Renewables & Energy

Coalburn 2 is a separate battery phase beside Coalburn 1 in South Lanarkshire.

Investor AIP and developer CIP target commissioning of Coalburn 2 in 2027.

Project details · Map

[1] · [2]

DP World London Gateway ExpansionBerth 5 opening2027Live · Expected

Transport

DP World’s London Gateway expansion adds container-handling and rail infrastructure to the Thames estuary port.

Berth 5 only; the full two-berth and rail-terminal programme retains its around-2029 target.

Project milestones

Project details · Map

[1] · [2]

Ellison Institute of Technology OxfordInitial campus2027Live · Expected

Research & Innovation

The Ellison Institute of Technology is building an interdisciplinary research and technology campus in Littlemore, at The Oxford Science Park. The University of Oxford reports that construction of the initial campus is expected to cost more than £1 billion.

This target refers to the initial campus, not completion of the entire expanded estate.

Project details · Map

[1] · [2]

Glasgow Airport UpgradeCompletion / operation2027Live · Expected

Transport

Glasgow Airport plans a terminal and gate-area overhaul with expanded shops, dining and supporting infrastructure.

Reported terminal-upgrade target.

Project details · Map

[1]

Glasgow Meet Our Waterfront — Clyde Riverside ParkPhased delivery2027–2030Approved · Expected

Urban Development & Housing

Glasgow City Council plans to turn the central River Clyde waterfront between Glasgow Bridge and Victoria Bridge into an accessible public park and a series of connected walking, cycling and gathering spaces. The Meet Our Waterfront scheme covers Custom House Quay on the north bank and Carlton Place on the south bank, creating new riverside routes and public spaces while addressing the declining condition of the quay walls that support and protect parts of the river frontage. The design by Hawkins\Brown, with engineering support from Civic, obtained planning consent in September 2026. The programme has not yet been confirmed as physically under construction.

Indicative construction period, subject to funding and procurement.

Project details · Map

[1]

Inch Cape Offshore Wind FarmCompletion / operation2027Live · Expected

Renewables & Energy

Inch Cape is a 1,142 MW offshore wind farm under construction off the Angus coast, with its grid connection in East Lothian.

Project details · Map

[1] · [2]

iREACHHealthCompletion / operation2027Live · Expected

Healthcare

iREACH Health is a £64 million clinical research programme centred on two new buildings on Lisburn Road beside Belfast City Hospital. The facilities will bring together clinical trials, healthcare research and industry collaboration.

Opening target; the buildings remain under construction.

Project details · Map

[1] · [2] · [3]

Leeds Bradford Airport Terminal RegenerationArrivals refurbishment2027Live · Expected

Transport

LBA:REGEN expands and refurbishes Leeds Bradford Airport’s terminal. The extension opened in 2025; refurbishment continues through later security and arrivals phases.

Operator forecast for the arrivals phase, not a certified whole-programme opening date.

Project milestones

Project details · Map

[1] · [2]

Lord’s Allen and Tavern stands redevelopmentAllen Stand completionWinter 2026/27Live · Expected

Heritage & Culture

MCC is redeveloping the Allen and Tavern stands at Lord’s in phases, with improved seating, spectator facilities and access.

MCC forecast for the Allen Stand; wider Tavern redevelopment follows.

Project milestones

Project details · Map

[1] · [2]

Matrix 500 MW Eccles BESSCompletion / operation2027Live · Expected

Renewables & Energy

Matrix Renewables’ Eccles battery is a separate Scottish Borders project from Zenobē’s nearby development.

Current project calendar targets November 2027 project completion; April 2026 financing release forecast commercial operation inQ3 2027. Distinct milestones and the later calendar require operational confirmation.

Project milestones

Project details · Map

[1] · [2] · [3]

Momentum One Zero innovation centreCompletion / operation2027Live · Expected

Research & Innovation

Queen’s University Belfast is expanding the ECIT innovation centre in the Titanic Quarter with new research laboratories, computing and collaboration space. The £37 million building forms part of the £70 million Momentum One Zero programme. Construction adds east and west extensions to the existing centre, rather than a separate campus.

Opening forecast for the expanded innovation centre.

Project details · Map

[1] · [2] · [3] · [4]

Nansledan, NewquayMarket Street first phaseEnd 2027Live · Expected
Pale terraced houses on Stret Myghtern Arthur in Nansledan
Homes on Stret Myghtern Arthur, Nansledan, May 2023
Photo creditMutney / Wikimedia Commons · CC BY-SA 4.0 · Original image · Compressed preview; display may crop.

Urban Development & Housing

Nansledan is a long-term urban extension on the eastern edge of Newquay, Cornwall, developed and managed by the Duchy of Cornwall. The 540-acre (approximately 218-hectare) masterplan will ultimately accommodate around 4,000 homes including associated third-party land, alongside shops, offices, employment space, schools, neighbourhood facilities and green areas. The Duchy's own project descriptions also use a figure of around 3,700 homes for the narrower Duchy-led development; the wider masterplan includes land beyond that development.

Duchy of Cornwall target for Tesco, the Market Hall and five shops.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Oaklands Farm Solar ParkCompletion / operationEnd of 2027 or early 2028Live · Expected

Renewables & Energy

Oaklands Farm Solar Park is a 151.1 MW solar development near Rosliston and Walton-on-Trent in South Derbyshire, connecting to the existing Drakelow substation.

BayWa operational forecast spans late 2027 and early 2028; no single-year opening implied.

Project details · Map

[1] · [2] · [3] · [4]

Olympia RedevelopmentBritish Airways Theatre2027Live · Expected

Urban Development & Housing

Olympia’s redevelopment adds hospitality and conference facilities around its historic London exhibition halls.

Expected opening of separate theatre phase.

Project milestones

Project details · Map

[1] · [2] · [3]

Peel Ports UK Warehousing ExpansionAlexandra Dock warehouse2027Live · Expected

Logistics & Manufacturing

Peel Ports Group is expanding its port-side warehousing at Liverpool and Glasgow. It announced a phased programme in October 2026 intended to add around one million square feet of storage, including new and upgraded facilities for goods such as fertiliser, chemicals and metals.

Forecast completion of the 130,000-square-foot building, not the whole programme.

Project details · Map

[1] · [2]

Piccadilly Line UpgradeFirst passenger serviceDecember 2026–June 2027Live · Expected

Transport

The Piccadilly Line Upgrade replaces 86 existing trains with 94 new trains and adapts depots, power supplies and platforms for them. First passenger service remains ahead.

Forecast introduction window; not whole-programme completion.

Project milestones

Project details · Map

[1] · [2]

Pulse Penn BESSGrid energisationEnd 2027Approved · Expected

Renewables & Energy

Pulse Penn is a battery storage project at Lower Penn, near Wolverhampton. METLEN describes its design as 129 MW / 362 MWh, while optimisation partner Statkraft describes the scheme as 128 MW.

METLEN forecast; commercial operation is a separate milestone.

Project milestones

Project details · Map

[1] · [2]

Royal Surrey Cancer and Surgical Innovation CentreCompletion / operation2027Live · Expected

Healthcare

Royal Surrey County Hospital has opened a £41.5 million Cancer and Surgical Innovation Centre on its Guildford campus. The purpose-built centre provides six operating theatres, specialist recovery facilities and the 24-bed Shalford short-stay ward.

Project details · Map

[1] · [2]

St Paul's Gyratory PedestrianisationPhase 1 streets2027Live · Expected

Urban Development & Housing

The St Paul’s gyratory project reorganises streets near the cathedral to create public space and improve walking and cycling routes while retaining vehicle access.

First-phase streets only; the Phase 2 programme has not been stated.

Project details · Map

[1] · [2]

TfL iBus2 Bus Information System UpgradeFleet installation2027–2029Live · Expected

Transport

Known as iBus2, the upgrade will introduce new computers on buses and trams, alongside a central system for processing their location and journey information. TfL awarded INIT a £160 million, ten-year contract in March 2024. The contract covers the new equipment, implementation and continuing services. The original programme scope covers approximately 8,850 buses and trams across London.

TfL’s March 2026 forecast for installation across the fleet.

Project details · Map

[1] · [2] · [3]

The Tofoo Co Malton FactoryCompletion / operation2027Live · Expected

Logistics & Manufacturing

The Tofoo Co is building a new food-manufacturing facility at Malton Enterprise Park, North Yorkshire. Designed to double its initial production capacity and provide 3.5 times its current productive space, the factory is expected to be completed in autumn 2027.

Project details · Map

[1] · [2]

UKAEA–Eni H3AT Tritium Loop FacilityAssembly of key systems2027Approved · Expected

Research & Innovation

UKAEA and Eni are developing the H3AT Tritium Loop Facility at Culham to test the fuel cycle needed by future fusion power plants.

UKAEA strategy target for system assembly and delivery of uranium beds.

Project milestones

Project details · Map

[1] · [2] · [3]

Windyhill battery storageCommercial operationQ4 2027 or Q1 2028Live · Expected

Renewables & Energy

Revera is building a battery energy storage system at Bearsden, north-west of Glasgow, close to the B6 transmission boundary.

Revera’s 23 September 2026 announcement gives Q4 2027. Its UK project page and 6 August announcement give Q1 2028; these forecasts remain inconsistent.

Project details · Map

[1] · [2] · [3]

Wrexham Stadium ExpansionNew Kop stand2027Live · Expected

Heritage & Culture

The Racecourse Ground redevelopment replaces Wrexham’s Kop stand as part of the club’s stadium expansion.

New Kop stand, ready for the 2027/28 season.

Project details · Map

[1] · [2]

Zenobē Eccles 400 MW BESSCompletion / operation2027Live · Expected

Renewables & Energy

Zenobē’s Eccles battery in the Scottish Borders is designed to reduce wasted wind energy and support the electricity network.

Project details · Map

[1]

2028

GE Aerospace Prestwick ExpansionCompletion / operationQ1 2028Approved · Expected

Logistics & Manufacturing

GE Aerospace plans to expand and modernise its existing engine maintenance, repair and overhaul site at Prestwick. A new 55,000 sq ft building and changes to the site layout, logistics and access are intended to increase capacity and improve operational flow.

Project details · Map

[1]

Golden Valley DevelopmentIDEA innovation centreEarly 2028Live · Expected

Research & Innovation

Golden Valley is a planned cyber and technology campus and neighbourhood in Cheltenham, developed by the council and HBD.

First innovation-centre phase target; whole Golden Valley completion is not confirmed.

Project details · Map

[1] · [2]

Noriker Kilmarnock South battery storageCompletion / operationEarly 2028Live · Expected

Renewables & Energy

Construction is under way on the 350-megawatt Kilmarnock South battery at Camsiscan Farm in South Ayrshire. Developed by Noriker and backed by Copenhagen Infrastructure Partners, the facility is designed to store electricity for several hours before supplying it back to the grid. Commercial operation is targeted for early 2028.

Owner’s construction target, retaining the stated early-year precision.

Project details · Map

[1]

Pulse Penn BESSCompletion / operationEarly 2028Approved · Expected

Renewables & Energy

Pulse Penn is a battery storage project at Lower Penn, near Wolverhampton. METLEN describes its design as 129 MW / 362 MWh, while optimisation partner Statkraft describes the scheme as 128 MW.

Statkraft’s operation forecast. METLEN’s end-2027 energisation target is a separate grid milestone, not full commercial operation.

Project milestones

Project details · Map

[1] · [2]

Twyn Hywel Energy ParkFull operationEarly 2028Live · Expected

Renewables & Energy

Construction began at Twyn Hywel Energy Park in June 2026. The development will have up to 93.8 MW of generating capacity, with turbines reaching a maximum height of 200 metres. Bute Energy secured £160 million of project debt financing from Lloyds and Rabobank after obtaining planning consent. It is the first wind farm in the developer’s Welsh portfolio to reach construction.

Developer forecast for full operation. First power is targeted for late 2027; final testing and restoration may continue into winter 2028.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

UK Next National Supercomputer — EdinburghService operationEarly 2028Live · Expected

Research & Innovation

A new UK national supercomputing facility is being built at the University of Edinburgh's EPCC Advanced Computing Facility. Known as the Next National Supercomputing Service, it is planned to succeed ARCHER2 as a major shared resource for academic and industrial research. The programme is backed by up to £750 million of UK Government investment. That figure covers a wider programme of physical infrastructure, power, computing hardware and operational support; it is not the cost of the building alone.

EPCC forecast for the national supercomputing service.

Project details · Map

[1]

Wellcome Genome Campus ExpansionFirst phaseEarly 2028Live · Expected

Research & Innovation

The Wellcome Genome Campus is expanding its genomics and biodata research site at Hinxton, south of Cambridge. The long-term plan adds laboratory and workspace buildings, homes and supporting facilities.

The campus’s March 2026 forecast for its first phase; the wider expansion is a longer-term programme.

Project details · Map

[1] · [2]

Four Lines ModernisationMetropolitan northern branches signalling (SMA13)H1 2028OFF
TRACK
Live · Revised target

Transport

TfL’s Four Lines Modernisation programme replaces trains and signalling across four Underground lines. The remaining programme principally concerns Metropolitan line signalling and software.

SMA13 has moved from H2 2027 to H1 2028; programme close-out is forecast for 2029.

Amersham, Chesham and Watford branches; revised commissioning forecast from H2 2027 to H1 2028.

Project milestones

Project details · Map

[1]

Golborne Rail StationCompletion / operationSpring 2028Live · Expected

Transport

Greater Manchester is building a fully accessible two-platform station at Golborne on the West Coast Main Line, restoring passenger rail access after more than 60 years.

Expected start of passenger services.

Project details · Map

[1] · [2]

UCL Institute of Neurology CampusResearch staff move-inSpring 2028Live · Expected

Healthcare

UCL is creating a neuroscience centre at 256 Grays Inn Road, including laboratories for the Institute of Neurology and dementia research.

UCL forecast following fit-out and testing.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Power Court StadiumCompletion / operationJune 2028Live · Expected

Heritage & Culture

Power Court is Luton Town’s new stadium under construction in Luton town centre, intended to replace Kenilworth Road.

Club target for stadium construction completion, ahead of the intended 2028–29 season opening.

Project details · Map

[1] · [2]

Leighton Hospital redevelopmentMain building work startsSummer 2028Approved · Expected

Healthcare

A replacement Leighton Hospital is planned north of the existing Crewe campus, as part of a wider health and care neighbourhood. The six-storey hospital has hybrid planning approval and a £1.35 billion budget, with 102,682 square metres of internal space.

Trust forecast; subject to programme approvals.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Manchester Airport Station UpgradeStation improvementsMid 2028Approved · Expected

Transport

Network Rail’s £115m programme with Kier will extend platforms 1–3, remodel track layouts and upgrade signalling at Manchester Airport station. Work is scheduled from winter 2026 to mid-2028.

Network Rail schedules the station works to run from the end of 2026 to mid-2028.

Project details · Map

[1] · [2]

RAF Waddington Airfield RefurbishmentCompletion / operationSummer 2028Live · Expected

Transport

The Defence Infrastructure Organisation is refurbishing aircraft bays, taxiways, drainage and approach lighting at RAF Waddington, the RAF hub for intelligence, surveillance, target acquisition and reconnaissance operations.

MOD completion expectation at the September 2026 construction start.

Project details · Map

[1]

South Crofty Tin Mine RedevelopmentFirst tin productionMid 2028Live · Expected

Logistics & Manufacturing

Cornish Metals is redeveloping South Crofty, which closed in 1998. Work includes dewatering and shaft refurbishment, winding equipment and a new processing plant. The mine has not resumed commercial tin production.

Company target for first tin production, dependent on financing completion, construction and remaining consents or variations.

Project details · Map

[1] · [2] · [3] · [4]

Wanlip sewage-treatment works upgradeCompletion / operationSummer 2028Live · Expected

Nature & Rewilding

Severn Trent is upgrading Wanlip Sewage Treatment Works in Leicestershire to increase wastewater treatment capacity and improve treatment performance.

Severn Trent’s project completion forecast.

Project details · Map

[1] · [2]

Matrix Kilmarnock Energy CentreCompletion / operationQ3 2028Approved · Expected

Renewables & Energy

Matrix Renewables is developing a 500-megawatt battery storage facility beside the Kilmarnock electricity substation in East Ayrshire. The project received consent in April 2025 and is progressing through surveys and preparation for construction. It would store electricity and return it to the network when needed.

Matrix’s indicative project completion target; actual construction commencement is not yet confirmed.

Project details · Map

[1] · [2] · [3]

Revera Hunterston BESS 400 MW / 800 MWhCompletion / operationQ3 2028Live · Expected

Renewables & Energy

Revera’s Hunterston Battery Energy Storage System is a 400 MW / 800 MWh project in North Ayrshire, Scotland, connecting to SP Energy Networks’ 400 kV transmission system.

Revera expects commercial operations in Q3 2028.

Project details · Map

[1] · [2]

West Park Student Residences — University of ExeterSecond accommodation phaseSeptember 2028Live · Expected

Urban Development & Housing

West Park is a major redevelopment of student housing at the University of Exeter

A further 1,231 bedrooms planned.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Four Lines ModernisationRayners Lane–Uxbridge signalling (SMA14)H2 2028OFF
TRACK
Live · Revised target

Transport

TfL’s Four Lines Modernisation programme replaces trains and signalling across four Underground lines. The remaining programme principally concerns Metropolitan line signalling and software.

SMA13 has moved from H2 2027 to H1 2028; programme close-out is forecast for 2029.

Final signalling migration area; programme close-out follows in 2029.

Project milestones

Project details · Map

[1]

Pembroke 350 MW BESSCompletion / operationH2 2028Approved · Expected

Renewables & Energy

RWE plans a battery facility beside Pembroke Power Station as part of its wider low-carbon energy programme.

RWE expects commissioning and operation in the second half of 2028, subject to an updated, timely grid connection.

Project details · Map

[1] · [2]

Brabazon New TownFirst Build-to-Rent apartmentsEnd of 2028Live · Expected

Urban Development & Housing

Brabazon is a new mixed-use neighbourhood on the former Filton Airfield near Bristol, with homes and supporting amenities delivered in phases.

First apartments in the 239-home project; a forecast for this phase.

Project details · Map

[1] · [2] · [3]

DLR Fleet ReplacementCompletion / operationEnd of 2028OFF
TRACK
Live · Revised target

Transport

TfL is introducing 54 new DLR trains with supporting depot works. Fleet introduction is phased; three trains were in passenger service at the October 2026 report.

End of 2026 → End of 2028. Full-fleet availability has moved from the earlier end-2026 expectation to end-2028.

Full-fleet availability forecast.

Project details · Map

[1] · [2]

East Anglia TWO Offshore Wind FarmCompletion / operationLate 2028Live · Expected

Renewables & Energy

East Anglia TWO is ScottishPower Renewables’ 960MW offshore wind farm under construction in the southern North Sea, around 33km from Suffolk at its nearest point. Its export connection comes ashore north of Thorpeness.

Developer target for commercial operation.

Project milestones

Project details · Map

[1] · [2]

Marchwood 200 MW BESSCompletion / operationLate 2028Approved · Expected

Renewables & Energy

BW ESS plans a battery energy storage facility at Marchwood Industrial Park on Southampton Water.

Reported operational forecast, not confirmation of commissioning.

Project details · Map

[1] · [2]

Rolls-Royce Sinfin A facilitiesCompletion / operationEnd of 2028Live · Expected

Logistics & Manufacturing

Rolls-Royce is building new engineering and manufacturing services facilities at its Sinfin A campus in Derby, with £112 million allocated to the redevelopment.

Target for the two new Sinfin A buildings to be ready. The broader Derby investment also includes aftermarket-support refurbishment.

Project details · Map

[1] · [2]

Twyn Hywel Energy ParkFinal worksWinter 2028Live · Expected

Renewables & Energy

Construction began at Twyn Hywel Energy Park in June 2026. The development will have up to 93.8 MW of generating capacity, with turbines reaching a maximum height of 200 metres. Bute Energy secured £160 million of project debt financing from Lloyds and Rabobank after obtaining planning consent. It is the first wind farm in the developer’s Welsh portfolio to reach construction.

Forecast for remaining energisation, testing and restoration.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

100 KensingtonFinal build completionEnd 2027 or early 2028Live · Expected

Urban Development & Housing

100 Kensington is a 462-home development on West Cromwell Road in west London, with seven buildings arranged around a central podium garden.

The developer’s restart announcement gives early 2028 in its programme but end 2027 in a quoted timetable.

Project milestones

Project details · Map

[1]

Airbus Belfast A220 Wing Factory ExtensionCompletion / operation2028Live · Expected

Logistics & Manufacturing

Airbus began building a 6,221m² extension to its Belfast wing-manufacturing facility in August 2026 to expand the production of composite wings for the A220 passenger aircraft. The development adds factory floorspace, specialist tooling and a third autoclave for curing carbon-fibre components.

Airbus expects the factory extension to be completed in the first half of 2028.

Project details · Map

[1] · [2] · [3]

Birmingham Airport upgradesWorks programme2025–29Live · Expected

Transport

Birmingham Airport is delivering a phased programme of arrivals, baggage-handling and airfield improvements through 2029. Works include aircraft stands, taxiways, runway repairs and terminal heating and cooling systems.

Programme period, rather than a confirmed completion date for every work package.

Project details · Map

[1]

Birmingham Eastside Metro — remaining stagesDigbeth Coach Station passenger services2028Live · Expected

Transport

The remaining Birmingham Eastside Metro extension connects Millennium Point with Curzon Street and Digbeth Coach Station. The Bull Street–Millennium Point section opened on 5 April 2026 and is outside this project’s remaining works.

WMCA’s forecast for services to Digbeth. Curzon Street stop will open later with the HS2 station.

Project details · Map

[1] · [2] · [3]

Cardiff Central station upgradeMost improvements2028Live · Expected

Transport

Cardiff Central’s upgrade will expand passenger space and improve facilities and accessibility at Wales’s busiest railway station.

Target for most enhancements, not a confirmed whole-station completion date.

Project details · Map

[1] · [2]

Cheadle Railway StationCompletion / operation2028Live · Expected

Transport

A new single-platform railway station is being built beside Alexandra Hospital on the Mid-Cheshire line, restoring passenger rail access to Cheadle.

Greater Manchester programme target for construction completion.

Project details · Map

[1] · [2]

Clarendon Square — Oxford City Centre RegenerationCompletion / operation2028Live · Expected

Urban Development & Housing

The former Clarendon Centre in central Oxford is being redeveloped into Clarendon Square, a new open-air public space surrounded by shops, restaurants and offices. The scheme replaces an enclosed 1980s shopping-centre layout with pedestrian connections between the historic streets around Cornmarket Street and Queen Street. Goldmoney Properties, through GP Clarendon Square Ltd, is delivering the project. The current approved design is by Quinlan Terry, with buildings and shopfronts intended to complement Oxford's historic centre.

Developer opening target, subject to construction and fit-out.

Project details · Map

[1] · [2]

Devilla 500 MW BESSCommissioning2028Live · Expected

Renewables & Energy

Devilla is a 500 MW, two-hour lithium-ion battery storage project at Kincardine, developed by Copenhagen Infrastructure Partners with Alcemi. The transmission-connected facility is intended to support grid stability and integration of renewable electricity.

CIP’s June 2026 commissioning forecast.

Project details · Map

[1]

Glasgow Meet Our Waterfront — Clyde Riverside ParkPhased delivery2027–2030Approved · Expected

Urban Development & Housing

Glasgow City Council plans to turn the central River Clyde waterfront between Glasgow Bridge and Victoria Bridge into an accessible public park and a series of connected walking, cycling and gathering spaces. The Meet Our Waterfront scheme covers Custom House Quay on the north bank and Carlton Place on the south bank, creating new riverside routes and public spaces while addressing the declining condition of the quay walls that support and protect parts of the river frontage. The design by Hawkins\Brown, with engineering support from Civic, obtained planning consent in September 2026. The programme has not yet been confirmed as physically under construction.

Indicative construction period, subject to funding and procurement.

Project details · Map

[1]

Harker Battery Storage (formerly Blackdyke Farm)Commercial operationLate 2028–early 2029Approved · Expected

Renewables & Energy

Zenobē’s planned 400 MW / 800 MWh Harker battery-storage facility near Carlisle was developed by Innova as Blackdyke BESS and acquired by Zenobē in 2025.

Developer forecast for commercial operation; grid energisation is a separate earlier milestone.

Project details · Map

[1] · [2] · [3]

Hartmoor BESSGrid energisation2028Live · Expected

Renewables & Energy

Hartmoor is Field’s 200 MW battery project near Hartlepool in north-east England.

Field’s July 2026 forecast is for grid energisation in 2028.

Project details · Map

[1]

London Museum at SmithfieldCompletion / operation2028Live · Expected
Dome and brickwork of the former Smithfield General Market during conversion
General Market during conversion — archive photograph, 31 March 2022
Photo creditMatt Brown; resized preview · CC BY 2.0 · Dome of the old Smithfield Market

Heritage & Culture

London Museum is moving into the former Victorian General Market at Smithfield, with the adjoining Poultry Market forming a later phase. The £437 million redevelopment reuses historic market buildings for permanent galleries, exhibition spaces, learning and collections facilities.

Poultry Market phase expected in 2028; General Market public opening scheduled for 28 November 2026.

Project milestones

Project details · Map

[1] · [2]

London Museum at SmithfieldPoultry Market2028Live · Expected
Dome and brickwork of the former Smithfield General Market during conversion
General Market during conversion — archive photograph, 31 March 2022
Photo creditMatt Brown; resized preview · CC BY 2.0 · Dome of the old Smithfield Market

Heritage & Culture

London Museum is moving into the former Victorian General Market at Smithfield, with the adjoining Poultry Market forming a later phase. The £437 million redevelopment reuses historic market buildings for permanent galleries, exhibition spaces, learning and collections facilities.

Temporary exhibitions, collections and learning facilities.

Project milestones

Project details · Map

[1] · [2]

Manchester Fallowfield campus redevelopmentFirst 1,000 rooms2028Live · Expected

Urban Development & Housing

The University of Manchester is redeveloping its Fallowfield accommodation campus with 3,300 student rooms and shared facilities, through a £530 million partnership.

Contractor’s opening forecast.

Project milestones

Project details · Map

[1] · [2]

New Cardiff Bay ArenaCompletion / operation2028Live · Expected

Heritage & Culture

The new Cardiff Bay Arena is a multi-purpose entertainment venue planned at Atlantic Wharf, forming part of a wider regeneration scheme.

Target opening for the arena.

Project details · Map

[1] · [2]

Oaklands Farm Solar ParkCompletion / operationEnd of 2027 or early 2028Live · Expected

Renewables & Energy

Oaklands Farm Solar Park is a 151.1 MW solar development near Rosliston and Walton-on-Trent in South Derbyshire, connecting to the existing Drakelow substation.

BayWa operational forecast spans late 2027 and early 2028; no single-year opening implied.

Project details · Map

[1] · [2] · [3] · [4]

Outer Dowsing 1.5 GW Wind FarmConstruction start2028Approved · Expected

Renewables & Energy

Outer Dowsing is a planned offshore wind farm developed jointly by TotalEnergies, Macquarie interests and Gulf Energy Development.

Current developer preparation target; earlier government announcement said as early as2027.

Project milestones

Project details · Map

[1] · [2]

Oxford United New StadiumCompletion / operation2028Approved · Expected

Heritage & Culture

Oxford United proposes a new stadium at the Triangle near Kidlington, north of Oxford.

Club target: ready for the 2028/29 season.

Project details · Map

[1] · [2] · [3] · [4]

Syngenta Biosciences Research CentreCompletion / operation2028Live · Expected

Research & Innovation

Syngenta’s BioSTaR centre at Jealott’s Hill will combine agricultural bioscience, analytical research and digital technology.

Project details · Map

[1] · [2]

TfL iBus2 Bus Information System UpgradeFleet installation2027–2029Live · Expected

Transport

Known as iBus2, the upgrade will introduce new computers on buses and trams, alongside a central system for processing their location and journey information. TfL awarded INIT a £160 million, ten-year contract in March 2024. The contract covers the new equipment, implementation and continuing services. The original programme scope covers approximately 8,850 buses and trams across London.

TfL’s March 2026 forecast for installation across the fleet.

Project details · Map

[1] · [2] · [3]

UCL Institute of Neurology CampusCompletion / operation2028Live · Expected

Healthcare

UCL is creating a neuroscience centre at 256 Grays Inn Road, including laboratories for the Institute of Neurology and dementia research.

UCLH expects the Grays Inn Road neuroscience centre to open in 2028.

Project milestones

Project details · Map

[1] · [2] · [3]

UKAEA–Eni H3AT Tritium Loop FacilityFacility completion2028Approved · Expected

Research & Innovation

UKAEA and Eni are developing the H3AT Tritium Loop Facility at Culham to test the fuel cycle needed by future fusion power plants.

UKAEA’s March 2026 forecast for facility completion.

Project milestones

Project details · Map

[1] · [2] · [3]

UKAEA–Eni H3AT Tritium Loop FacilityInactive commissioning2028Approved · Expected

Research & Innovation

UKAEA and Eni are developing the H3AT Tritium Loop Facility at Culham to test the fuel cycle needed by future fusion power plants.

UKAEA strategy target for initial inactive commissioning.

Project milestones

Project details · Map

[1] · [2] · [3]

Wednesbury–Dudley–Merry Hill Metro extensionCompletion / operation2028Live · Expected

Transport

The West Midlands Metro is being extended from Wednesbury through Tipton and Dudley to Merry Hill in Brierley Hill. The new line will connect these Black Country communities to the existing tram network. Delivery is phased: the Dudley section is undergoing testing and commissioning, while construction continues towards Merry Hill.

The 2028 forecast applies to the extension to Merry Hill. The first section to Dudley is being tested; passenger services on that section will follow commissioning and driver training.

Project details · Map

[1]

Windyhill battery storageCommercial operationQ4 2027 or Q1 2028Live · Expected

Renewables & Energy

Revera is building a battery energy storage system at Bearsden, north-west of Glasgow, close to the B6 transmission boundary.

Revera’s 23 September 2026 announcement gives Q4 2027. Its UK project page and 6 August announcement give Q1 2028; these forecasts remain inconsistent.

Project details · Map

[1] · [2] · [3]

2029

Piccadilly Line UpgradeFull fleet replacementQ4 FY 2028/29Live · Expected

Transport

The Piccadilly Line Upgrade replaces 86 existing trains with 94 new trains and adapts depots, power supplies and platforms for them. First passenger service remains ahead.

Q4 forecast in TfL’s October paper; under review.

Project milestones

Project details · Map

[1] · [2]

Derriford Emergency Care BuildingCompletion / operationApril 2029Live · Expected

Healthcare

Derriford Hospital's Emergency Care Building is a four-storey expansion of urgent, emergency, imaging and surgical capacity for Plymouth, Devon and Cornwall.

Target for completion of the Emergency Care Building.

Project details · Map

[1] · [2]

Newarthill 300 MW BESSGrid energisationOctober 2029Approved · Expected

Renewables & Energy

Newarthill is a 300 MW battery storage project near Motherwell in North Lanarkshire, developed by Elements Green. The planned two-hour configuration would store 600 MWh, with potential to extend to four hours.

Developer target; not a confirmed commercial-operation date.

Project details · Map

[1]

Corscale Court Lane data-centre campusPractical completionQ4 2029Approved · Expected

Digital Infrastructure

Corscale’s planned Court Lane campus at Iver would replace a 14-acre industrial estate beside the M25 with two data-centre buildings and an on-site substation.

McLaren’s announced practical-completion target.

Project details · Map

[1]

Awel y Môr 800 MW Wind FarmOffshore construction starts2029Approved · Expected

Renewables & Energy

Awel y Môr is an offshore wind project west of the existing Gwynt y Môr farm off north Wales.

Earliest indicative developer date.

Project milestones

Project details · Map

[1] · [2]

Beacon Fen Energy ParkCompletion / operation2029OFF
TRACK
Approved · Previous target

Renewables & Energy

Beacon Fen Energy Park is a consented solar and battery-storage development east of Sleaford and north of Heckington, linked to Bicker Fen substation.

The legal challenge creates uncertainty over delivery.

Low Carbon’s forecast for operation.

Project details · Map

[1] · [2] · [3]

Birmingham Airport upgradesWorks programme2025–29Live · Expected

Transport

Birmingham Airport is delivering a phased programme of arrivals, baggage-handling and airfield improvements through 2029. Works include aircraft stands, taxiways, runway repairs and terminal heating and cooling systems.

Programme period, rather than a confirmed completion date for every work package.

Project details · Map

[1]

Bramford Storage — ClearstoneCompletion / operation2029Approved · Expected

Renewables & Energy

Clearstone Energy is developing a battery storage facility outside Bramford, near Ipswich in Suffolk. The approved project would connect beside National Grid’s Bramford substation. Clearstone targets operation in 2029.

Clearstone’s target for the facility to enter operation; the date remains a forecast.

Project details · Map

[1] · [2]

DP World London Gateway ExpansionOverall expansion completionAround 2029Live · Expected

Transport

DP World’s London Gateway expansion adds container-handling and rail infrastructure to the Thames estuary port.

The March 2025 announcement described a four-year construction programme starting that May.

Project milestones

Project details · Map

[1]

Elsham Tech ParkFirst phase opening2029Approved · Expected

Digital Infrastructure

Elsham Tech Park is a proposed AI data-centre campus in North Lincolnshire.

First phase; construction expected from 2027.

Project details · Map

[1]

Eryri Visual Impact ProvisionPylon and overhead-line removal2029Live · Expected

Renewables & Energy

National Grid is moving the electricity connection across the Dwyryd Estuary into a 3.4 km tunnel between Minffordd and Llandecwyn. Once the underground connection is operating, ten pylons and roughly 3 km of overhead line can be removed, opening up views across the estuary and the western edge of Eryri National Park.

National Grid targets removal of the existing pylons and overhead line in 2029, after the underground connection becomes operational. The exact cable energisation date is unconfirmed.

Project details · Map

[1] · [2] · [3]

Four Lines ModernisationProgramme close-out2029OFF
TRACK
Live · Revised target

Transport

TfL’s Four Lines Modernisation programme replaces trains and signalling across four Underground lines. The remaining programme principally concerns Metropolitan line signalling and software.

SMA13 has moved from H2 2027 to H1 2028; programme close-out is forecast for 2029.

Programme close-out after signalling and software completion.

Project milestones

Project details · Map

[1]

Frodsham Solar — CheshireCompletion / operation2029Approved · Expected

Renewables & Energy

Frodsham Solar is a nationally significant solar photovoltaic and battery-storage project proposed on land north of Frodsham in Cheshire. Developed by Cubico Sustainable Investments through Frodsham Solar Limited, it is designed to generate low-carbon electricity for the regional network and potentially supply nearby industrial users directly.

Developer target for operation; preparatory works expected in 2027.

Project details · Map

[1] · [2]

Glasgow Meet Our Waterfront — Clyde Riverside ParkPhased delivery2027–2030Approved · Expected

Urban Development & Housing

Glasgow City Council plans to turn the central River Clyde waterfront between Glasgow Bridge and Victoria Bridge into an accessible public park and a series of connected walking, cycling and gathering spaces. The Meet Our Waterfront scheme covers Custom House Quay on the north bank and Carlton Place on the south bank, creating new riverside routes and public spaces while addressing the declining condition of the quay walls that support and protect parts of the river frontage. The design by Hawkins\Brown, with engineering support from Civic, obtained planning consent in September 2026. The programme has not yet been confirmed as physically under construction.

Indicative construction period, subject to funding and procurement.

Project details · Map

[1]

Great Ormond Street Hospital Children’s Cancer CentreCompletion / operation2029Live · Expected

Healthcare

Great Ormond Street’s Children’s Cancer Centre will replace the existing frontage building with specialist cancer care and supporting hospital facilities.

Great Ormond Street Hospital anticipates opening the Children’s Cancer Centre to patients in 2029.

Project details · Map

[1] · [2] · [3]

Harker Battery Storage (formerly Blackdyke Farm)Commercial operationLate 2028–early 2029Approved · Expected

Renewables & Energy

Zenobē’s planned 400 MW / 800 MWh Harker battery-storage facility near Carlisle was developed by Innova as Blackdyke BESS and acquired by Zenobē in 2025.

Developer forecast for commercial operation; grid energisation is a separate earlier milestone.

Project details · Map

[1] · [2] · [3]

Havant Thicket ReservoirPipeline completion2029Live · Expected

Critical Infrastructure

Portsmouth Water is building an 8.7-billion-litre reservoir north of Havant, with two pipelines to fill it from local springs and supply water when needed.

Portsmouth Water’s May 2026 forecast for the pipelines; reservoir operation is separately forecast for 2032.

Project milestones

Project details · Map

[1] · [2] · [3]

HMP Welland OaksCompletion / operation2029Live · Expected

Critical Infrastructure

HMP Welland Oaks is a Category B prison under construction beside HMP Gartree near Market Harborough. It is designed to provide approximately 1,700 places when it opens, with the first prisoners expected in early 2029.

Project details · Map

[1] · [2] · [3] · [4]

Jacobs Wells Baths RestorationArts venue reopening2029Live · Expected

Heritage & Culture

Trinity Community Arts is restoring the Grade II former baths for cultural, dance and community use under a long-term lease from Bristol City Council.

Target for the broader arts-venue reopening, contingent on later restoration stages and funding. Not the first-phase completion date.

Project milestones

Project details · Map

[1] · [2]

M&S Automated Distribution CentreCompletion / operation2029Live · Expected

Logistics & Manufacturing

Marks & Spencer is building an automated national food-distribution centre in Daventry, Northamptonshire, with Prologis.

Project details · Map

[1] · [2]

TfL iBus2 Bus Information System UpgradeFleet installation2027–2029Live · Expected

Transport

Known as iBus2, the upgrade will introduce new computers on buses and trams, alongside a central system for processing their location and journey information. TfL awarded INIT a £160 million, ten-year contract in March 2024. The contract covers the new equipment, implementation and continuing services. The original programme scope covers approximately 8,850 buses and trams across London.

TfL’s March 2026 forecast for installation across the fleet.

Project details · Map

[1] · [2] · [3]

West of Orkney 2 GW Wind FarmFirst generation2029Approved · Expected

Renewables & Energy

West of Orkney is an offshore wind farm planned north of mainland Scotland and west of Orkney.

Developer target for first generation; its project page says first power is scheduled by 2030. Not full commissioning.

Project details · Map

[1] · [2]

2030

Transpennine Route UpgradeFull-route electrificationEarly 2030Live · Expected

Transport

The Transpennine Route Upgrade is a programme of railway improvements across the approximately 70-mile Manchester–Huddersfield–Leeds–York corridor, including electrification, additional tracks, signalling, station improvements and work on bridges and level crossings.

Delivery partnership forecast for electrification across the Manchester–Huddersfield–Leeds–York corridor.

Project milestones

Project details · Map

[1] · [2]

UK Robotics Adoption Hubs Programme (2026–2030)Programme endsMarch 2030Live · Expected

Research & Innovation

The programme brings together universities, specialist facilities, manufacturers and public services to test equipment, develop demonstrations and assess where automation could improve their work. The government announced £40 million for the eight hubs in October 2026, within UKRI’s wider £52 million Robotics Adoption Programme running from April 2026 to March 2030. Most hubs use existing facilities, with funding for expertise, shared testing, demonstration equipment, research and adoption support.

End of the national programme period. Individual services, trials and equipment deployments have separate delivery dates.

Project details · Map

[1] · [2]

130 Fenchurch StreetTower completion2030Approved · Expected

Urban Development & Housing

Aviva and CO-RE plan a 31-storey office tower at 130 Fenchurch Street in the City of London, replacing Fountain House.

Forecast in the City Corporation’s September 2025 announcement.

Project details · Map

[1]

85 Gracechurch StreetTower completion2030Approved · Expected

Urban Development & Housing

85 Gracechurch Street is an office tower planned beside Leadenhall Market in the City of London, with public spaces displaying remains of Roman London’s first basilica.

Woods Bagot’s March 2026 programme targets a 2027 construction start and completion in 2030.

Project details · Map

[1] · [2] · [3]

A9 Dualling — Pitlochry to KilliecrankieCompletion / operationEnd 2030Live · Expected

Transport

Transport Scotland is preparing to upgrade 6.4 kilometres of the A9 trunk road between Pitlochry and Killiecrankie from single to dual carriageway. The scheme is a component of the wider programme to dual the A9 between Perth and Inverness and aims to improve journeys, road safety and resilience along a major Scottish north-south transport corridor. It will provide new dual-carriageway road sections, grade-separated junctions and improvements for walking and cycling, with associated bridge and drainage construction.

Transport Scotland aims to open the dual carriageway by the end of 2030.

Project details · Map

[1] · [2]

Barbican Centre renewalPhase 1 completion2030Approved · Expected
A view across the Barbican Arts Centre terrace before the renewal programme.
The Barbican Arts Centre before renewal; photograph date unknown, uploaded in February 2003
Photo creditNevilley · CC BY-SA 3.0 · Barbican-arts-centre-large · Compressed preview; display may crop.

Heritage & Culture

The Barbican Centre renewal repairs and upgrades the Grade II-listed arts complex in London, restoring its Conservatory, foyers and lakeside terrace.

The operator’s target for the first phase of renewal.

Project details · Map

[1] · [2]

Cambridge Children's HospitalHospital building completion2030Approved · Expected

Healthcare

Cambridge Children’s Hospital is a proposed specialist hospital for the East of England, bringing physical and mental healthcare together with research.

Published construction target; operational opening is forecast separately for 2031.

Project milestones

Project details · Map

[1] · [2] · [3] · [4]

Camden Film QuarterFirst-phase completion2030Approved · Expected

Urban Development & Housing

Camden Film Quarter is an approved mixed-use development on the former Holmes Road Depot and Regis Road site in Kentish Town, combining film and television production, homes and education.

Engineering partner’s first-phase forecast.

Project details · Map

[1]

Devizes Assize Court — Wiltshire MuseumCompletion / operation2030Live · Expected

Heritage & Culture

Wiltshire Museum is transforming the former Devizes Assize Court, a Grade II*-listed courthouse built in 1835, into its new main exhibition and visitor venue. The project aims to rescue a prominent historic building that closed as a court in 1983 and has remained largely unused for decades, while creating modern galleries and public facilities for Wiltshire's significant archaeological collections. The project, known as Assizes for Devizes: Unlocking Wiltshire's Stories, received planning and listed-building consent in August 2025 and an £8.5 million heritage grant that December. On 26 October 2026, funded enabling works began on site, moving the redevelopment from planning into physical delivery. The museum is aiming for an opening in 2030.

Museum opening target; main restoration and further fundraising remain.

Project details · Map

[1] · [2]

Gatwick Airport Northern Runway ProjectCompletion / operation2030Approved · Expected

Transport

Gatwick plans to bring its existing northern runway into routine use, with associated infrastructure and operational changes.

This is an anticipated runway operating date; other project works could continue beyond it.

Project details · Map

[1] · [2]

Glasgow Meet Our Waterfront — Clyde Riverside ParkPhased delivery2027–2030Approved · Expected

Urban Development & Housing

Glasgow City Council plans to turn the central River Clyde waterfront between Glasgow Bridge and Victoria Bridge into an accessible public park and a series of connected walking, cycling and gathering spaces. The Meet Our Waterfront scheme covers Custom House Quay on the north bank and Carlton Place on the south bank, creating new riverside routes and public spaces while addressing the declining condition of the quay walls that support and protect parts of the river frontage. The design by Hawkins\Brown, with engineering support from Civic, obtained planning consent in September 2026. The programme has not yet been confirmed as physically under construction.

Indicative construction period, subject to funding and procurement.

Project details · Map

[1]

Hinkley Point C Nuclear Power StationFirst reactor start-up2030OFF
TRACK
Live · Revised target
Cranes and buildings under construction at Hinkley Point C
Hinkley Point C construction in March 2026
Photo creditChris Allen · CC BY-SA 2.0 · Hinkley Point C power station construction - geograph.org.uk - 8290825 · Resized preview.

Renewables & Energy

Hinkley Point C is a two-reactor nuclear power station under construction in Somerset.

2029 → 2030. The first reactor’s expected start has moved back by a year.

EDF’s 2025 Universal Registration Document, filed in March 2026, expects Unit 1 to start production in 2030. This is a first-reactor milestone.

Project details · Map

[1] · [2] · [3] · [4]

Leeds Existing Station Programme — £303m Station TransformationCompletion / operation2030Approved · Expected

Transport

Leeds railway station is to undergo a £303 million expansion and redesign to increase passenger capacity, improve accessibility and reduce congestion at one of Britain's busiest regional rail hubs.

Project details · Map

[1]

Manchester Fallowfield campus redevelopmentCompletion / operation2030Live · Expected

Urban Development & Housing

The University of Manchester is redeveloping its Fallowfield accommodation campus with 3,300 student rooms and shared facilities, through a £530 million partnership.

The contractor forecasts the remaining rooms completing by 2030.

Project milestones

Project details · Map

[1] · [2]

Outer Dowsing 1.5 GW Wind FarmFirst power2030Approved · Expected

Renewables & Energy

Outer Dowsing is a planned offshore wind farm developed jointly by TotalEnergies, Macquarie interests and Gulf Energy Development.

Government forecast; not a whole-project completion date.

Project milestones

Project details · Map

[1] · [2]

Statera Sundon 500 MW BESSCompletion / operation2030Approved · Expected

Renewables & Energy

Sundon Storage is Statera’s consented battery project, intended to store surplus renewable electricity and release it during higher demand.

Target for full operation; long-duration configuration is conditional.

Project details · Map

[1] · [2]

UKAEA–Eni H3AT Tritium Loop FacilityActive commissioning2030Approved · Expected

Research & Innovation

UKAEA and Eni are developing the H3AT Tritium Loop Facility at Culham to test the fuel cycle needed by future fusion power plants.

UKAEA’s strategy envisages active commissioning under way by 2030; a March announcement expected full commissioning in 2030.

Project milestones

Project details · Map

[1] · [2] · [3]

Windermere Wastewater and Storm Overflow UpgradesFurther treatment and overflow schemes2030Live · Expected

Nature & Rewilding

United Utilities is upgrading wastewater treatment and storm overflow storage across the Windermere catchment. The programme is valued at up to £200 million and covers 15 projects: improvements at nine treatment works and additional storage at six storm overflows. Some improvements are complete and construction continues at other sites.

Operator expects specified further schemes to be completed by 2030; individual schemes follow their own programmes.

Project milestones

Project details · Map

[1] · [2]

2031

Awel y Môr 800 MW Wind FarmFirst generation2031Approved · Expected

Renewables & Energy

Awel y Môr is an offshore wind project west of the existing Gwynt y Môr farm off north Wales.

Earliest indicative developer date; no generation has been confirmed.

Project milestones

Project details · Map

[1] · [2]

Cambridge Children's HospitalOperational opening2031Approved · Expected

Healthcare

Cambridge Children’s Hospital is a proposed specialist hospital for the East of England, bringing physical and mental healthcare together with research.

Cambridge Biomedical Campus’s published opening forecast; indicative and subject to programme approvals.

Project milestones

Project details · Map

[1] · [2] · [3]

Edinburgh Airport Terminal TransformationInvestment programme ends2031Live · Expected

Transport

Edinburgh Airport's Terminal Transformation is a five-year capital programme to expand and modernise Scotland's busiest airport.

The investment programme is planned over five years.

Project milestones

Project details · Map

[1]

Equinix 250 MW Data CentreCampus operational2031Approved · Expected

Digital Infrastructure

Equinix plans a data-centre campus east of South Mimms services in Hertfordshire. The company acquired the 85-acre site in 2025 and plans to invest £3.9 billion in a campus with more than 250 MW of capacity.

Operator forecast aligned with the planned grid connection.

Project details · Map

[1] · [2]

Great Oak Energy HubCompletion / operation2031Approved · Expected

Renewables & Energy

Great Oak Energy Hub is a consented 400 MW battery storage project on the Knepp Estate, south of Horsham in Sussex. Clearstone Energy targets operation in 2031.

Clearstone’s target for the battery to become operational.

Project details · Map

[1]

HMP Garth 2Completion / operation2031Approved · Expected

Critical Infrastructure

HMP Garth 2 is a planned category C prison beside the existing Garth and Wymott prisons near Leyland.

Project details · Map

[1]

Mars Melton Mowbray Pet Food Factory ModernisationCompletion / operation2031Approved · Expected

Logistics & Manufacturing

Mars is investing £161 million in its Melton Mowbray pet food factory, with modernisation planned through 2031. The programme includes new high-speed pouch lines, automated handling and improved manufacturing controls.

Project details · Map

[1] · [2]

Natural History Museum’s Shinfield centreCentre fully operational2031Live · Expected

Heritage & Culture

The Natural History Museum’s collections, science and digitisation centre at Shinfield will bring together specimen storage, research laboratories and digitisation facilities.

Museum forecast following the collections move.

Project milestones

Project details · Map

[1]

South Kensington Station UpgradeCompletion / operation2031Approved · Expected

Transport

Transport for London is preparing a capacity and accessibility upgrade of South Kensington Underground station. Minor preparatory works have begun at 34 Thurloe Street, the future step-free entrance, while the main station works are planned from 2028.

TfL target for full delivery, not a confirmed opening date.

Project details · Map

[1] · [2] · [3] · [4] · [5]

Universal UK ProjectCompletion / operation2031Live · Expected
Cleared former brickworks site at Kempston Hardwick
Former Kempston Hardwick brickworks site in July 2024; no resort is shown
Photo creditMark Anderson · CC BY-SA 2.0 · Site of the Kempston Hardwick brickworks - geograph.org.uk - 7924334 · Resized preview.

Heritage & Culture

Universal United Kingdom Resort is a planned theme park and resort near Bedford, with themed attractions and a hotel.

The theme park and resort are planned to open in 2031. Further investment will continue after opening.

Project details · Map

[1] · [2]

2032

British Library St Pancras ExtensionCompletion / operation2032Live · Expected
The existing British Library building and courtyard in London.
The existing British Library courtyard and building, 2 March 2025; the extension is not shown
Photo creditCarol Benovic-Bradley · CC BY 2.0 · British Library 2025-03-02 · Resized preview; display may crop.

Heritage & Culture

The British Library’s St Pancras extension combines new public library facilities with commercial space in London’s Knowledge Quarter.

Developer and architect target; opening has not occurred.

Project details · Map

[1] · [2]

Havant Thicket ReservoirCompletion / operation2032Live · Expected

Critical Infrastructure

Portsmouth Water is building an 8.7-billion-litre reservoir north of Havant, with two pipelines to fill it from local springs and supply water when needed.

Forecast start of reservoir operation.

Project milestones

Project details · Map

[1] · [2] · [3]

Junction 27 Energy HubCompletion / operation2032Approved · Expected

Renewables & Energy

Junction 27 Energy Hub is an approved 400 MW battery storage project near Westleigh in Devon. Around six hectares of infrastructure sit within a wider landscaped site.

Developer’s target for operation.

Project details · Map

[1]

Leighton Hospital redevelopmentCompletion / operationFY 2032/33Approved · Expected

Healthcare

A replacement Leighton Hospital is planned north of the existing Crewe campus, as part of a wider health and care neighbourhood. The six-storey hospital has hybrid planning approval and a £1.35 billion budget, with 102,682 square metres of internal space.

Trust’s planned hospital opening; main works expected in summer 2028.

Project milestones

Project details · Map

[1] · [2] · [3]

Lower Thames CrossingCompletion / operation2032–2033Live · Expected

Transport

The Lower Thames Crossing is a planned road and tunnel connection between Kent and Essex, east of the Dartford Crossing.

Anticipated opening; subject to the final funding programme.

Project details · Map

[1] · [2]

Royal College of Art Kensington Campus RenewalCompletion / operation2032Live · Expected

Research & Innovation

Phased renewal of the Royal College of Art’s Kensington campus centres on the listed Darwin Building, with new teaching spaces and modernised studios and workshops.

College forecast for completion of the phased campus programme.

Project details · Map

[1]

2033

Granton Waterfront Regeneration — EdinburghPhase one2033Live · Expected

Urban Development & Housing

Granton Waterfront is a large-scale regeneration of former industrial waterfront land on the Firth of Forth in north Edinburgh. The council-led programme aims to create a new coastal neighbourhood, with approximately 3,500 homes alongside public facilities, shops, workplaces, walking and cycling routes, and major new green spaces. It is being delivered through multiple physical phases rather than a single building project. Early completed or active developments in the wider district include Granton Station restoration, housing at Granton Station View and Western Villages, and work at Silverlea. A further major 847-home phase led by Cruden Group is now under construction.

Target for the 847-home first phase, not the entire waterfront programme.

Project details · Map

[1] · [2]

Leighton Hospital redevelopmentCompletion / operationFY 2032/33Approved · Expected

Healthcare

A replacement Leighton Hospital is planned north of the existing Crewe campus, as part of a wider health and care neighbourhood. The six-storey hospital has hybrid planning approval and a £1.35 billion budget, with 102,682 square metres of internal space.

Trust’s planned hospital opening; main works expected in summer 2028.

Project milestones

Project details · Map

[1] · [2] · [3]

Lower Thames CrossingCompletion / operation2032–2033Live · Expected

Transport

The Lower Thames Crossing is a planned road and tunnel connection between Kent and Essex, east of the Dartford Crossing.

Anticipated opening; subject to the final funding programme.

Project details · Map

[1] · [2]

One London — 1 UndershaftCompletion / operation2033Live · Expected
Demolition of St Helen's Tower, June 2026
St Helen's Tower during demolition, June 2026
Photo creditMatt Brown / Wikimedia Commons · CC BY 4.0 · Original image · Image resized and may be cropped.

Urban Development & Housing

One London is a 74-storey skyscraper planned for the heart of the City of London, beside the Gherkin and the Leadenhall Building. At 309.6 metres, it is designed to become the joint-tallest building in the UK alongside The Shard, and the tallest in the City of London.

Target for the replacement tower; main construction is scheduled to begin in 2028.

Project details · Map

[1] · [2]

2034

City Centre South, CoventryCompletion / operation2034Live · Expected

Urban Development & Housing

City Centre South is a residential-led mixed-use regeneration of Coventry city centre, developed by The Hill Group and Shearer Property Group. The council’s current listing describes a 6.5-hectare site.

Council forecast for the wider programme.

Project details · Map

[1] · [2]

2035

Dinorwig Pumped Storage ReplantingCompletion / operation2035Live · Expected

Renewables & Energy

Dinorwig is a 1.8 GW pumped-storage power station in Gwynedd, North Wales. Its replanting programme is modernising ageing generating units to extend the station’s operating life and retain its rapid-response storage capacity.

Full refurbishment of all six units.

Project details · Map

[1] · [2] · [3]

Smithfield RegenerationCompletion / operation2035Approved · Expected

Urban Development & Housing

Smithfield is a mixed-use regeneration of Birmingham’s former wholesale market area, including a new market neighbourhood.

Expected completion of the full redevelopment.

Project details · Map

[1] · [2] · [3]

2036

2037

North West Quadrant — Slough Town Centre RegenerationCompletion / operation2037Approved · Expected

Urban Development & Housing

North West Quadrant is a proposed mixed-use redevelopment of the former Thames Valley University campus immediately beside Slough railway station. The 3.68-hectare site has been vacant since the university closed and its remaining structures were removed.

Project details · Map

[1]

2038

Kensal CanalsideCompletion / operation2038Approved · Expected

Urban Development & Housing

Kensal Canalside is a proposed redevelopment of Sainsbury’s and former utility land beside the Grand Union Canal in west London. The Ballymore and Sainsbury’s scheme includes 2,519 homes, a replacement supermarket, a community hub and new public green spaces.

Developer target for all works on the Sainsbury’s and former utility-land site, subject to the remaining planning process and future construction progress.

Project details · Map

[1] · [2]

York Central RegenerationCompletion / operation2038Approved · Expected

Urban Development & Housing

York Central is a 45-hectare regeneration beside York railway station, led by McLaren Property and Arlington Real Estate on behalf of Homes England and Network Rail.

Indicative programme for the final masterplan phase.

Project details · Map

[1] · [2]

2039

Sizewell C Nuclear Power StationCompletion / operation2039–2043Live · Expected
Cranes and piling equipment at the Sizewell C construction site
Sizewell C construction site in October 2025
Photo creditHugh Venables · CC BY-SA 2.0 · Sizewell C construction site (geograph 8176167) · Resized preview.

Renewables & Energy

Sizewell C is a nuclear power station under construction on the Suffolk coast. Its two planned reactors are intended to supply electricity for around six million homes.

The Public Accounts Committee reported in October 2026 that the project was expected to be fully operational in 2039 and gave a 2039–2043 construction completion range.

Project details · Map

[1] · [2] · [3]

2040

Euston Station RedevelopmentFull HS2 scheme including Euston opens2040–2043Approved · Expected
Excavation and construction works at Euston
HS2 construction work at Euston in September 2024
Photo creditStephen McKay · CC BY-SA 2.0 · HS2 work at Euston - geograph.org.uk - 7876460 · Resized preview.

Transport

The Euston Station Campus programme combines a new HS2 terminus with redevelopment of the existing Network Rail station, London Underground improvements and surrounding mixed-use development.

May 2026 government estimate: May 2040 to December 2043 for the full scheme including Euston and Handsacre Junction; not an independent completion estimate for the entire station campus.

Project details · Map

[1] · [2]

Sizewell C Nuclear Power StationCompletion / operation2039–2043Live · Expected
Cranes and piling equipment at the Sizewell C construction site
Sizewell C construction site in October 2025
Photo creditHugh Venables · CC BY-SA 2.0 · Sizewell C construction site (geograph 8176167) · Resized preview.

Renewables & Energy

Sizewell C is a nuclear power station under construction on the Suffolk coast. Its two planned reactors are intended to supply electricity for around six million homes.

The Public Accounts Committee reported in October 2026 that the project was expected to be fully operational in 2039 and gave a 2039–2043 construction completion range.

Project details · Map

[1] · [2] · [3]

STEP FusionCompletion / operation2040Approved · Expected

Renewables & Energy

STEP Fusion is the UK programme to design and deliver a prototype spherical-tokamak fusion power plant at the former West Burton A power-station site in Nottinghamshire.

Target for the prototype plant to begin operations.

Project details · Map

[1] · [2] · [3]

2041

Earls Court RedevelopmentCompletion / operation2041Approved · Expected

Urban Development & Housing

The Earls Court redevelopment proposes a new mixed-use neighbourhood on the former exhibition centre site across two London boroughs.

Expected completion of the full redevelopment.

Project details · Map

[1] · [2] · [3]

Euston Station RedevelopmentFull HS2 scheme including Euston opens2040–2043Approved · Expected
Excavation and construction works at Euston
HS2 construction work at Euston in September 2024
Photo creditStephen McKay · CC BY-SA 2.0 · HS2 work at Euston - geograph.org.uk - 7876460 · Resized preview.

Transport

The Euston Station Campus programme combines a new HS2 terminus with redevelopment of the existing Network Rail station, London Underground improvements and surrounding mixed-use development.

May 2026 government estimate: May 2040 to December 2043 for the full scheme including Euston and Handsacre Junction; not an independent completion estimate for the entire station campus.

Project details · Map

[1] · [2]

Sizewell C Nuclear Power StationCompletion / operation2039–2043Live · Expected
Cranes and piling equipment at the Sizewell C construction site
Sizewell C construction site in October 2025
Photo creditHugh Venables · CC BY-SA 2.0 · Sizewell C construction site (geograph 8176167) · Resized preview.

Renewables & Energy

Sizewell C is a nuclear power station under construction on the Suffolk coast. Its two planned reactors are intended to supply electricity for around six million homes.

The Public Accounts Committee reported in October 2026 that the project was expected to be fully operational in 2039 and gave a 2039–2043 construction completion range.

Project details · Map

[1] · [2] · [3]

2042

Euston Station RedevelopmentFull HS2 scheme including Euston opens2040–2043Approved · Expected
Excavation and construction works at Euston
HS2 construction work at Euston in September 2024
Photo creditStephen McKay · CC BY-SA 2.0 · HS2 work at Euston - geograph.org.uk - 7876460 · Resized preview.

Transport

The Euston Station Campus programme combines a new HS2 terminus with redevelopment of the existing Network Rail station, London Underground improvements and surrounding mixed-use development.

May 2026 government estimate: May 2040 to December 2043 for the full scheme including Euston and Handsacre Junction; not an independent completion estimate for the entire station campus.

Project details · Map

[1] · [2]

Sizewell C Nuclear Power StationCompletion / operation2039–2043Live · Expected
Cranes and piling equipment at the Sizewell C construction site
Sizewell C construction site in October 2025
Photo creditHugh Venables · CC BY-SA 2.0 · Sizewell C construction site (geograph 8176167) · Resized preview.

Renewables & Energy

Sizewell C is a nuclear power station under construction on the Suffolk coast. Its two planned reactors are intended to supply electricity for around six million homes.

The Public Accounts Committee reported in October 2026 that the project was expected to be fully operational in 2039 and gave a 2039–2043 construction completion range.

Project details · Map

[1] · [2] · [3]

Teviot Estate RedevelopmentCompletion / operation2042Live · Expected

Urban Development & Housing

Poplar HARCA and The Hill Group are regenerating the Teviot Estate in Tower Hamlets in phases, with up to 1,928 new homes, public space and community facilities. Phase one is under way and will provide 475 homes.

Poplar HARCA expects the full estate regeneration to be complete by 2042; homes will be delivered in phases.

Project details · Map

[1] · [2] · [3]

2043

Euston Station RedevelopmentFull HS2 scheme including Euston opens2040–2043Approved · Expected
Excavation and construction works at Euston
HS2 construction work at Euston in September 2024
Photo creditStephen McKay · CC BY-SA 2.0 · HS2 work at Euston - geograph.org.uk - 7876460 · Resized preview.

Transport

The Euston Station Campus programme combines a new HS2 terminus with redevelopment of the existing Network Rail station, London Underground improvements and surrounding mixed-use development.

May 2026 government estimate: May 2040 to December 2043 for the full scheme including Euston and Handsacre Junction; not an independent completion estimate for the entire station campus.

Project details · Map

[1] · [2]

Sizewell C Nuclear Power StationCompletion / operation2039–2043Live · Expected
Cranes and piling equipment at the Sizewell C construction site
Sizewell C construction site in October 2025
Photo creditHugh Venables · CC BY-SA 2.0 · Sizewell C construction site (geograph 8176167) · Resized preview.

Renewables & Energy

Sizewell C is a nuclear power station under construction on the Suffolk coast. Its two planned reactors are intended to supply electricity for around six million homes.

The Public Accounts Committee reported in October 2026 that the project was expected to be fully operational in 2039 and gave a 2039–2043 construction completion range.

Project details · Map

[1] · [2] · [3]